A Review of the Current State of Lean Construction in Nairobi City
County
Joyreen Mwende Ngei
1
, Sylvester Munguti Masu
2
, Lucy M. Nyabwengi
3
The Technical University of Kenya, Nairobi, Kenya
DOI: https://doi.org/10.51244/IJRSI.2025.120800307
Received: 02 Sep 2025; Accepted: 08 Sep 2025; Published: 08 October 2025
ABSTRACT
The construction industry in Nairobi City County, Kenya, plays a critical role in urban development but
continues to face challenges related to inefficiencies, cost overruns, and waste generation. Lean Construction
(LC), a philosophy derived from the Toyota Production System, offers a framework for enhancing productivity
through waste minimization and value creation. This article reviews the current state of LC implementation in
Nairobi City County by drawing on both global literature and empirical findings from recent field research.
The study reveals that while awareness of LC is relatively high (70%), actual implementation remains low
(36%), with tools such as 5S, Just-in-Time (JIT), and the Last Planner System (LPS) being partially applied.
The most significant waste sources identified were inventory waste (58%), labour inefficiency (53%), and
waiting time (41%). Barriers to implementation include lack of awareness, resistance to change, fragmented
supply chains, and inadequate training. The findings highlight the potential of LC in addressing inefficiencies,
but greater institutional support, capacity building, and policy integration are necessary to realize its full
benefits in Nairobis construction sector.
Keywords: Lean Construction, Waste Management, Nairobi City County, 5S, Just-in-Time, Last Planner
System
INTRODUCTION
The construction industry contributes significantly to Kenya’s economic growth, accounting for approximately
7% of the national GDP. However, the sector is characterized by inefficiencies manifested in project delays,
cost overruns, and high levels of material waste. This study focuses on Nairobi City County, as Kenya's capital
and largest urban area; it is at the forefront of the country's construction activities as evidenced by NCA that it
records the highest number of building permits (NCA, n. d). The county's construction projects are often large-
scale and complex, making them prime candidates for lean construction techniques. The county experiences
rapid urbanization and infrastructural development, resulting in a high volume of construction projects.
However, like the rest of the country, Nairobi's construction sector is plagued by inefficiencies and waste levels
are particularly high, undermining both profitability and sustainability. The implementation of lean
construction techniques in Nairobi could provide a model for the rest of the country. According to Wachira
(2020), a case study done of Nairobi City County's construction projects reveals that adopting lean construction
can lead to significant waste reduction and enhanced efficiency. Studies show that projects, which have
implemented lean methodologies, such as pull planning and value stream mapping, have reported a 30%
reduction in waste and a 20% decrease in project delays. These results underscore the potential of lean
construction to transform the construction landscape in Nairobi and beyond (Nganga, 2020).
Lean Construction (LC) has emerged as an alternative project management philosophy aimed at reducing
waste and enhancing efficiency. Originating from the Toyota Production System, LC emphasizes value
INTERNATIONAL JOURNAL OF RESEARCH AND SCIENTIFIC INNOVATION (IJRSI)
ISSN No. 2321-2705 | DOI: 10.51244/IJRSI |Volume XII Issue IX September 2025
Page 3392
www.rsisinternational.org
generation for the client while systematically eliminating non-value-adding activities (Koskela, 1992). Lean
construction aims to improve efficiency, reduce waste, and enhance quality and safety on construction sites.
Internationally, the adoption of lean construction has demonstrated significant improvements in project
delivery and waste management. For instance, a study by Azhar et al. (2013) highlighted that lean construction
techniques reduced construction waste by up to 60% and improved project completion times by 30% in several
case studies across the United States and Europe. Globally, lean tools such as 5S, Just-in-Time (JIT),
Kaizen,and the Last Planner System (LPS) have demonstrated effectiveness in improving project delivery.
However, the uptake of these tools in Africa, and specifically Nairobi, remains relatively low. This review
explores the current state of LC adoption in Nairobi, drawing on both empirical findings and literature.
LITERATURE REVIEW
Lean Construction was derived from Lean Production whose foundation commenced with the introduction of
Toyota Production System (TPS) spearheaded by Taiichi Ohno of Toyota Motor Company (Ohno, 1988). TPS
aimed at removing any kind of waste and inconsistency in the production system. TPS consists of two pillars
that are Just-in-Time (JIT) and Jidoka (Ohno, 1988; Liker, 2004; [Jasti et al., 2014]). According to Sacks et al.
(2020), the foundation of lean construction was formed through the proposition of the transformationflow
value (TFV) theory by Koskela (1992) and the development of the lean project delivery system by Ballard
(2003). TFV refers to the conceptualization of the production process through three key elements, which are
transformation that is, production of inputs into outputs; flow which is movement that is reliable and
continuous; and value, that is, what the customer needs and pays for it ([Ajayi et al., 2019]; Nguyen &
Arkhavian, 2019;). Lean project delivery system, according to Ballard and Howell (2023), links five phases of
the lifecycle, which are project definition, lean design, lean supply, lean assembly, and use. The lean project
delivery system addresses construction as production, and reliable production management is of prime
importance in lean project delivery systems, which is realized by utilizing the last planner system. Globally, the
implementation of lean construction varies significantly across regions. In developed economies, lean practices
are often integrated with digital technologies such as Building Information Modelling (BIM) ([Sacks et al.,
2020]). In contrast, African contexts face structural and institutional barriers, including inadequate training and
fragmented project delivery systems (Aigbavboa & Thwala, 2019).
Studies in Uganda and Nigeria have reported similar challenges, where lean awareness is moderate but
adoption is weak due to cultural resistance and resource limitations ([Alinaitwe et al., 2019]). In Kenya, while
lean principles have been acknowledged in academic discourse, empirical evidence of widespread application
remains limited.
RESEARCH METHODOLOGY
This review draws on both secondary literature and primary research conducted in Nairobi City County. A
mixed-methods design was adopted to provide a comprehensive perspective. Survey research through
Structured questionnaires were administered to 132 construction professionals, including contractors, project
managers, site supervisors, engineers, Architects and quantity surveyors. A five-point Likert scale was used to
assess awareness, familiarity and implementation, of lean practices. 10 semi-structured interviews were
conducted with senior engineers, Contractors and project managers to capture deeper insights into challenges
and opportunities of lean adoption. Additionally, Direct observations were carried out across eight active
building construction sites to verify the extent of lean application in practice and to identify visible sources of
waste. Quantitative data were analyzed using descriptive statistics (SPSS) and Chi-square tests to examine
relationships between lean practices and waste reduction. Qualitative data from interviews and observations
were coded thematically to capture emerging patterns. This methodology ensured triangulation of findings,
enhancing both reliability and validity.
INTERNATIONAL JOURNAL OF RESEARCH AND SCIENTIFIC INNOVATION (IJRSI)
ISSN No. 2321-2705 | DOI: 10.51244/IJRSI |Volume XII Issue IX September 2025
Page 3393
www.rsisinternational.org
RESULTS AND DISCUSSION
Awareness Levels
Survey data showed that 70% of construction professionals in Nairobi are aware of LC principles. This
demonstrates growing recognition of LC as a viable approach to project management. However, awareness is
often theoretical rather than practical, with limited exposure to structured lean training programs.
Table 4.1: Awareness of Lean
No. of Respondents
Frequency
Aware
92
69.69
Unaware
40
30.30
Source: Study survey, 2025
Ayarkwa et al. (2021) argue that awareness is critical for effective uptake of lean construction practices in
emerging markets. This shows that most of the respondents (70%) were aware of lean construction in the
industry
Implementation of Lean Tools
Table 4.2 shows the level of implementation of lean construction within building sites as reported by the
respondents. The data showed that 38% of the respondents implemented lean construction moderately within
their construction sites. Whereas 25% of the respondents indicated that they rarely implemented lean
construction practices.
Table 4.2: Level of Lean Implementation
Percentage
Yes, extensively
12.12%
Yes, Moderately
37.88%
Rarely
25%
Not at all
15.15%
Not sure
9.84%
Source: Study survey, 2025
A study done by Ahmed et. al. (2020), showed that the level of lean construction implementation in Sri Lanka
was not rigid and the awareness minimal, whereas a comparison with the United Kingdom Construction
Industry showed that awareness was increased and implementation of lean construction practices were also
more evident. Additionally, a study done by Marhani et. Al. (2019) showed that with increased awareness of
lean construction practices, there was an increased implementation of lean practices within construction sites.
INTERNATIONAL JOURNAL OF RESEARCH AND SCIENTIFIC INNOVATION (IJRSI)
ISSN No. 2321-2705 | DOI: 10.51244/IJRSI |Volume XII Issue IX September 2025
Page 3394
www.rsisinternational.org
A review of the familiarity and extent of implementation of Lean construction practices within the construction
sites showed that that JIT Material delivery, Value engineering, 5S site organization for improving site
organization, Modular construction, and visual management and are the most familiar lean construction
practices. Additionally, Value engineering, 5S site organization, JIT Material Delivery for minimizing excess
inventory and storage costs, and The Last Planner system for enhancing scheduling accuracy and reducing
waiting time often used within building sites
Other tools such as Value Stream Mapping (VSM), Kaizen, and Total Quality Management (TQM) were rarely
implemented, reflecting a gap between awareness and comprehensive application.
These findings align with Ballard & Tommelein (2021), who asserted that JIT and 5S were easier to adopt due
to their simplicity and immediate impact. Conversely, tools like VSM and Pull Planning require more training
and cultural change, often lacking in Nairobi’s construction ecosystem (Nganga, 2020). [Zhang et al., 2021]
emphasized on stakeholder collaboration through Last Planner System (LPS) and Value engineering were
extensively used due to their effectiveness in reducing reworks and defects through collaborative planning.
Challenges in Implementation
Key barriers to the implementation of Lean practices within Nairobi City County was identified as Lack of
awareness and training rated as the most significant challenge to implementation. Unfamiliarity with lean tool,
Poor collaboration and communication, and resistance to change rated as significant challenges as well. High
initial implementation costs, Inadequate management support, lack of skilled personnel and limited resources
rated as moderately significant challenges. Cultural barriers ranked the lowest.
A Chi-square test of independence conducted indicated that lack of awareness/training, unfamiliarity with
tools, and poor collaboration were the most dominant challenges, consistent with findings by Olarewaju &
Abdul-Aziz (2020), who found awareness and training as the top barriers in Nigeria; as well as Alaloul et al.
(2020), whose study showed that limited collaboration and fragmented communication to be critical challenges
in implementing lean construction.
CONCLUSION AND RECOMMENDATIONS
The results revealed that Nairobi City’s construction industry is familiar with lean concepts, however, its worth
in waste management has not been fully leveraged. The data supports the assertion that lean construction, when
effectively implemented, can significantly reduce waste and subsequent inefficiencies on building sites. The
partial use of lean construction practices such as JIT delivery, 5S and value engineering already contributes to
more efficient practices. The research underscores the need for systemic and strategic interventions in training,
policy integration, and demonstration projects to bridge the current implementation gap.
Furthermore, this review establishes that while awareness of LC in Nairobi City County is relatively high,
practical implementation remains low.
To enhance the implementation of lean construction within construction building sites within Nairobi City
County the following recommendations can be taken up:
Capacity Building: Introduce continuous professional development (CPD) programs on LC.
Policy Integration: Mainstream LC practices into national construction codes and procurement guidelines.
Pilot Projects: Launch government-supported pilot lean projects to showcase benefits.
INTERNATIONAL JOURNAL OF RESEARCH AND SCIENTIFIC INNOVATION (IJRSI)
ISSN No. 2321-2705 | DOI: 10.51244/IJRSI |Volume XII Issue IX September 2025
Page 3395
www.rsisinternational.org
Collaboration: Encourage partnerships between contractors, suppliers, and academia to localize lean practices.
The findings underscore the need for a coordinated approach to embed LC into Kenya’s construction industry,
ensuring improved efficiency, cost savings, and sustainability.
REFERENCES
1. Aigbavboa, C., & Thwala, W. D. (2019). Resistance to lean practices in the African
construction industry. Journal of Construction Research, 6(3), 124135.
2. Alinaitwe, H., Mwakali, J., & Hansson, B. (2019). Assessing lean construction in Uganda.
Journal of Civil Engineering and Management, 25(4), 312321.
3. Aziz, R. F., & Hafez, S. M. (2019). Applying lean thinking in construction and performance
improvement. Alexandria Engineering Journal, 58(2), 639652.
4. Ajayi, S. O., & Oyedele, L. O. (2018). Critical design factors for minimising waste in
construction projects: A structural equation modelling approach. Resources, Conservation and
Recycling, 137, 302-313. https://doi.org/10.1016/j.resconrec.2018.05.022
5. Ayarkwa, J., Adinyira, E., & Osei-Asibey, D. (2020). Lean construction tools and techniques
in developing countries: A Ghanaian case study. Journal of Engineering, Design and
Technology, 18(6), 12831299. https://doi.org/10.1108/JEDT-09-2019-0243
6. Azhar, S., Ahmad, I., & Sein, M. K. (2013). Action research as a proactive research
methodology in the construction industry. Construction Management and Economics, 31(9),
705-718.
7. Ballard, G., & Howell, G. (2003). Lean project management. Building Research &
Information, 31(2), 119-133.
8. Ballard, G., & Howell, G. (2020). Lean construction: A guide to implementation. Routledge.
9. Jasti, N. V. K., & Kodali, R. (2014). Lean production: literature review and trends.
International Journal of Production Research, 53(3), 867885.
https://doi.org/10.1080/00207543.2014.937508
10. Koskela, L. (1992). Application of the New Production Philosophy to Construction. CIFE
Technical Report No. 72.
11. Liker, J. K. 2004. The Toyota Way: 14 Management Principles from the World’s Greatest
Manufacturer. New York: McGraw-Hill.
12. Marhani, M. A., Jaapar, A., & Bari, N. A. (2019). Lean construction: Towards enhancing
sustainable construction in Malaysia. Construction Management and Economics, 37(6), 373-
392. https://doi.org/10.1080/01446193.2019.1566627
13. Nganga, P. (2020). The impact of lean construction on project efficiency in Nairobi. Journal of
Sustainable Construction, 12(1), 24-35.
14. Nguyen, P.; Akhavian, R. (2019) Synergistic effect of integrated project delivery, lean
construction, and building information modeling on project performance measures: A
quantitative and qualitative analysis. Adv. Civ. Eng., 1267048.
15. Ohno, T. 1988. The Toyota Production System: Beyond Large-scale Production. Portland, OR:
Productivity Press
16. Olanrewaju, A. L., & Abdul-Aziz, A. R. (2020). Organizational challenges to lean construction
implementation in Africa: A critical review. Journal of Construction in Developing Countries,
25(1), 89108. https://doi.org/10.21315/jcdc2020.25.1.6
17. Sacks, R., Koskela, L., Dave, B. A., & Owen, R. (2020). Interaction of Lean and BIM in
Construction. Wiley.
18. Wachira, C. (2020). Lean construction: A case study of waste reduction in Nairobi construction
projects. Master’s Thesis, Kenyatta University.
19. Zhang, L., Chen, L., Liu, Y., & Song, Y. (2021). Integrated Project Delivery (IPD) and Last
Planner System (LPS) in large-scale hospital construction projects: A case study. Journal of
Cleaner Production, 278, 123948. https://doi.org/10.1016/j.jclepro.2020.123948