Assessment of Schedule Performance on Project Delivery: The Architects’ Perspective, Enugu Metropolis
Authors
Department of Architecture FES, ESUT (Nigeria)
Article Information
DOI: 10.51244/IJRSI.2026.1305000171
Subject Category: Architecture
Volume/Issue: 13/5 | Page No: 1901-1908
Publication Timeline
Submitted: 2026-05-06
Accepted: 2026-05-12
Published: 2026-06-06
Abstract
The construction industry is a critical sector in national development, contributing significantly to economic growth, infrastructure provision, and employment generation. In construction industry, there need to plan a schedule to deliver the projects being undertaken. The timely delivery of projects is combination of many peoples’ duties including the architect. This paper tried to assess the role of the architect in managing schedule and time in a construction project. Through an in-depth literature review and a survey of practicing architects (in government and private offices) involved in project design, documentation, and supervision in Enugu metropolis. The study adopts a descriptive research approach using a survey design and purposive sampling. A total of one hundred (100) was purposively selected for this survey. It recommends that architect is very necessary and be invited early to any project.
Keywords
Architects’ perspective, Assessment, project delivery
Downloads
References
1. Aibinu, A. A., and Jagboro, G. O. (2002). "The Effects of Construction Delays on Project Delivery in Nigerian Construction Industry." International Journal of Project Management, 20(8), 593-599. [Google Scholar] [Crossref]
2. Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon. International Journal of Project Management, 17(6), 337–342. [Google Scholar] [Crossref]
3. Baratta, A. (2006) The triple constraint a triple illusion. PMI [Google Scholar] [Crossref]
4. Brown, L. (2025) Project delivery management; key methods and phases explained. [Google Scholar] [Crossref]
5. Cattani, G., Ferriani, S., Frederiksen, L and Taube, F. (2011) Project based organizing and strategic management. Advances in strategic management vol 28. Leeds England: Emerald. ISBN 978-1780521930 [Google Scholar] [Crossref]
6. Chan, D. W. M., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1), 55–63. [Google Scholar] [Crossref]
7. Esselink, B. (2000) A practical guide to localization. Amsterdam/Philadelphia: John Benjamins publishing company. ISBN: 978-9-027-21956-5 [Google Scholar] [Crossref]
8. Kerzner, (2017) Project management: a systems approach to planning, scheduling and controlling. 12 edition, Wiley, Hoboken. [Google Scholar] [Crossref]
9. Mansfield, N. R., Ugwu, O. O., & Doran, T. (1994). Causes of delay and cost overruns in Nigerian construction projects. International Journal of Project Management, 12(4), 254–260. [Google Scholar] [Crossref]
10. Mastt. (2025). Managing project schedules in Mastt. Mastt Help Center. https://help.mastt.com/knowledge/managing-project-schedules-in-mastt [Google Scholar] [Crossref]
11. Mesly, O. (2016) Project feasibility: tools for uncovering points of vulnerability. CRC press. Taylor and Francis. ISBN: 9781498757911 [Google Scholar] [Crossref]
12. Nicholas, J. M., & Steyn, H. (2020). Project management for engineering, business and technology (6th ed.). Routledge. [Google Scholar] [Crossref]
13. Nokes, S., and Kelly, S. (2007) The definitive guide to project management: the fast track to getting the job done on time and on budget. Pearson Education, Prentice Hall financial times. ISBN: 9780273710974 [Google Scholar] [Crossref]
14. Ogunsemi, D. R., & Jagboro, G. O. (2006). Time-cost model for building projects in Nigeria. Construction Management and Economics, 24(3), 253–258. [Google Scholar] [Crossref]
15. Oladapo, A. A. (2007). An investigation into the use of ICT in the Nigerian construction industry. ITcon, 12, 261–277. [Google Scholar] [Crossref]
16. Philip, J. (2004) PMP project management professional study guide: McGraw-Hill/Osborne. ISBN: 0072230622 [Google Scholar] [Crossref]
17. Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® Guide) (6th ed.). PMI. [Google Scholar] [Crossref]
18. Project Management Institute (PMI) (2021) A Guide to the Project Management Body of Knowledge (PMBOK® Guide). [Google Scholar] [Crossref]
19. Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. [Google Scholar] [Crossref]
Metrics
Views & Downloads
Similar Articles
- Re-Validating the Uniqueness of Urban Morphology of the Shekhawati Region Through Reconnaissance Using Hotspot Analysis
- Golden Ages and Emerging Needs: Rethinking old Age Homes as Self Sustained Communities
- The Missing Link between Colonial Jack Arch Roofing and Indigenous Construction Practices in India
- Archiving Kolakopa - A Study on the Present Condition and the Architectural Features of an Evanescing Historic Settlement.
- Analysing Vendor Lock-In in Serverless Architectures