Nigeria's Arbitration and Mediation Act 2023: Implications for Dispute Resolution in PPPS Road Infrastructure Projects in Nigeria – A Systematic Review

Authors

Ibrahim-Giwa Gholahan Victor

Department of Quantity Surveying, Baze University, Abuja (Nigeria)

Funmilola Helen Omoniwa

Department of Quantity Surveying, Baze University, Abuja (Nigeria)

Olusola Ogunsina

Department of Quantity Surveying, Baze University, Abuja (Nigeria)

Usman Hassan

Department of Quantity Surveying, Baze University, Abuja (Nigeria)

Article Information

DOI: 10.51244/IJRSI.2026.1307000431

Subject Category: Engineering & Technology

Volume/Issue: 13/7 | Page No: 5899-5913

Publication Timeline

Submitted: 2026-08-14

Accepted: 2026-08-19

Published: 2026-08-24

Abstract

Public-Private Partnerships (PPPs) have become critical mechanisms for addressing Nigeria's infrastructure deficit, yet the complex nature of road PPPs makes them prone to disputes that undermine project viability. Nigeria enacted the Arbitration and Mediation Act 2023 (AMA 2023) in May 2023, establishing a modern unified framework for arbitration and mediation, but its implications for road infrastructure PPP disputes remain underexplored. This paper systematically reviews literature to examine the implications of the AMA 2023 for dispute resolution in road infrastructure PPP projects, focusing on key provisions, current dispute resolution mechanisms, contextual factors influencing effectiveness, and implementation gaps between legal reform and practice. A systematic literature review following PRISMA guidelines was conducted across six databases (Scopus, Web of Science, Google Scholar, HeinOnline, AJOL, and ICRC publications) for sources published between January 2000 and February 2025. After screening 412 initial records, 87 sources were included for final synthesis, using thematic analysis guided by Braun and Clarke's six-phase framework. The AMA 2023 introduces significant innovations, including mandatory stay of court proceedings, electronic arbitration agreements, third-party funding, emergency arbitration, joinder and consolidation provisions, and statutory mediation with enforceable settlement agreements. However, the review identifies persistent implementation gaps associated with weak institutional capacity, political instability, land acquisition conflicts, economic volatility, corruption, and fragmented regulatory frameworks. The Lagos-Ibadan Expressway concession illustrates how inadequately addressed social and political risks can undermine project sustainability. The review concludes that legal reform alone cannot ensure effective dispute resolution. Realising the AMA 2023's potential requires PPP-specific dispute protocols, public-sector capacity building, integration of AMA provisions into standard contracts, dispute prevention mechanisms, and ethical guidance for emerging provisions. The study highlights the need to align formal legal reform with the institutional and relational realities of Nigerian road PPPs.

Keywords

Arbitration and Mediation Act 2023, Public-Private Partnerships, Dispute resolution, Road infrastructure, systematic review.

Downloads

References

1. Adesanya, D. S. (2025). Mediation in Nigeria: A review of Part II of the Arbitration and Mediation Act 2023. Nigerian Journal of Alternative Dispute Resolution, 9(1), 45-62. [Google Scholar] [Crossref]

2. Adewale, P. O., Aigbavboa, C., & Thwala, W. D. (2020). Critical success factors for public-private partnership implementation in Nigerian infrastructure projects. Journal of Engineering, Design and Technology, 18(6), 1723-1743. [Google Scholar] [Crossref]

3. African Development Bank. (2010). *Federal Republic of Nigeria: Country strategy paper 2010-2013*. Abidjan: African Development Bank. [Google Scholar] [Crossref]

4. Ahatty, S., Adaku, E., Ndekugri, I. E., & Oladimin, O. (2021). Dispute resolution in Public Private Partnership (PPP) infrastructure projects in Nigeria: Literature review. International Journal of Engineering Research & Technology, 10(9), 245-258. [Google Scholar] [Crossref]

5. Ajaelu, H. C., & Okereke, R. A. (2020). Arbitration as an alternative to litigation in construction projects. International Journal of Management and Humanities, 4(9), 166-172. [Google Scholar] [Crossref]

6. Andrews, M. (2013). The limits of institutional reform in development: Changing rules for realistic solutions. Cambridge University Press. [Google Scholar] [Crossref]

7. APMG International. (2021). PPP certification guide: Dispute resolution. Retrieved from https://ppp-certification.com [Google Scholar] [Crossref]

8. Babatunde, S. O., Opawole, A., & Akinsiku, O. E. (2012). Critical success factors in public-private partnership (PPP) on infrastructure delivery in Nigeria. Journal of Facilities Management, 10(3), 212-225. [Google Scholar] [Crossref]

9. Babatunde, S. O., Perera, S., Udeaja, C., & Zhou, L. (2013). Challenges in implementing public private partnership strategy for infrastructure delivery in Nigeria. In Proceedings of the Public Private Partnerships International Conference (PPP 2013): Body of Knowledge (pp. 433-440). University of Central Lancashire. [Google Scholar] [Crossref]

10. Babatunde, S. O., Perera, S., Zhou, L., & Udeaja, C. (2015). Barriers to public-private partnership projects in developing countries: A Nigerian case study. Engineering, Construction and Architectural Management, 22(6), 669-691. [Google Scholar] [Crossref]

11. Berkeley Law. (2023). Comparative perspectives on arbitration reform in emerging economies. Berkeley Center for Law and Business. [Google Scholar] [Crossref]

12. Braun, V., & Clarke, V. (2006). Using thematic analysis in psychology. Qualitative Research in Psychology, 3(2), 77-101. [Google Scholar] [Crossref]

13. Campbell, D. (Ed.). (2001). The relational theory of contract: Selected works of Ian Macneil. Sweet & Maxwell. [Google Scholar] [Crossref]

14. Davis, P., Ellis, J., & Cheung, S. (2023). Institutional challenges in PPP infrastructure delivery in Nigeria. Journal of Construction in Developing Countries, 28(1), 45-68. [Google Scholar] [Crossref]

15. DiMaggio, P. J., & Powell, W. W. (1983). The iron cage revisited: Institutional isomorphism and collective rationality in organizational fields. American Sociological Review, 48(2), 147-160. [Google Scholar] [Crossref]

16. Fadeyi, M. O., Kehinde, J. O., Nwachukwu, C., Adegbuyi, A., & Agboola, M. (2018). Governance challenges in public-private partnership projects in Nigeria. Journal of Engineering, Design and Technology, 16(3), 401-418. [Google Scholar] [Crossref]

17. Faruk Sani, A. (2022). Legal challenges and prospects in the ICRC framework for PPPs in Nigeria. Asian Law & Policy Review, 7(2), 112-128. [Google Scholar] [Crossref]

18. Foster, V., & Briceno-Garmendia, C. (2010). Africa's infrastructure: A time for transformation. Washington, DC: World Bank. [Google Scholar] [Crossref]

19. Freeman, R. E. (1984). Strategic management: A stakeholder approach. Pitman. [Google Scholar] [Crossref]

20. Harisankar, K. S., & Sreeparvathy, G. (2004). Rethinking dispute resolution in public-private partnerships for infrastructure development in India. Journal of Infrastructure Development, 6(1), 21-35. [Google Scholar] [Crossref]

21. Harmon, K. M. J. (2003). Effectiveness of dispute review boards. Journal of Construction Engineering and Management, 129(6), 674-679. [Google Scholar] [Crossref]

22. Helmke, G., & Levitsky, S. (2004). Informal institutions and comparative politics: A research agenda. Perspectives on Politics, 2(4), 725-740. [Google Scholar] [Crossref]

23. Ibrahim, A. D., Price, A. D. F., & Dainty, A. R. J. (2006). The analysis and allocation of risks in public-private partnerships in infrastructure projects in Nigeria. Journal of Financial Management of Property and Construction, 11(3), 149-163. [Google Scholar] [Crossref]

24. Ibrahim, J., Loch, C., & Sengupta, K. (2022). Two express road rehabilitation projects. In How megaprojects are damaging Nigeria and how to fix it: A practical guide to mastering very large government projects (pp. 161–175). Palgrave Macmillan. https://doi.org/10.1007/978-3-030-96474-0_9 [Google Scholar] [Crossref]

25. Infrastructure Concession Regulatory Commission (ICRC). (2012). Making PPP for infrastructure development happen: The Nigerian experience. Abuja: ICRC. [Google Scholar] [Crossref]

26. International Bar Association. (2025). Nigeria's Arbitration and Mediation Act 2023: Key innovations and global alignment. IBA Arbitration Committee Report. [Google Scholar] [Crossref]

27. International Journal of Project Engineering and Management Science (IJPREMS). (2025). Multilevel escalation in PPP dispute resolution. IJPREMS Special Issue, 15-32. [Google Scholar] [Crossref]

28. Ite, U. E. (2018). Public-private partnerships and sustainable development in Nigeria: Governance challenges and opportunities. Journal of Sustainable Development in Africa, 20(3), 45-62. [Google Scholar] [Crossref]

29. Itu, M., & Kenigua, W. E. (2021). The role of public-private partnership (PPP) on infrastructural development in Nigeria. Journal of Global Social Sciences, 2(5), 23-43. [Google Scholar] [Crossref]

30. Keating Chambers. (2025). Nigeria's Arbitration and Mediation Act 2023: Key reforms and implications. London: Keating Chambers. [Google Scholar] [Crossref]

31. LawGlobal Hub. (2025). Arbitration and mediation reforms under Nigeria's AMA 2023. Retrieved from https://www.lawglobalhub.com [Google Scholar] [Crossref]

32. Macneil, I. R. (1978). Contracts: Adjustment of long-term economic relations under classical, neoclassical, and relational contract law. Northwestern University Law Review, 72(6), 854-905. [Google Scholar] [Crossref]

33. Macneil, I. R. (1980). The new social contract: An inquiry into modern contractual relations. Yale University Press. [Google Scholar] [Crossref]

34. Meyer, J. W., & Rowan, B. (1977). Institutionalized organizations: Formal structure as myth and ceremony. American Journal of Sociology, 83(2), 340-363. [Google Scholar] [Crossref]

35. Mondaq. (2025). *Nigeria: Arbitration and Mediation Act 2023 - An overview of key changes*. Retrieved from https://www.mondaq.com [Google Scholar] [Crossref]

36. Mudi, A., Lowe, J., & Manase, D. (2015). Challenges of implementing public-private partnerships (PPPs) in Nigeria's road infrastructure. Proceedings of the 8th CIDB Conference, Johannesburg, 156-168. [Google Scholar] [Crossref]

37. Musenero, M., Ochieng, E., & Price, A. D. F. (2023). Effectiveness of dispute resolution mechanisms in infrastructure projects. ARCOM Proceedings, 345-356. [Google Scholar] [Crossref]

38. National Planning Commission. (2020). *National Integrated Infrastructure Master Plan (NIIMP) 2020-2040*. Abuja: Federal Government of Nigeria. [Google Scholar] [Crossref]

39. National Policy on Public-Private Partnership in Nigeria. (2008). Policy document prepared by the Infrastructure Concession Regulatory Commission. Abuja: ICRC. [Google Scholar] [Crossref]

40. Nigerian Institute of Chartered Arbitrators (NICArb). (2024). *Third-party funding and the Arbitration and Mediation Act 2023*. NICArb Policy Brief. [Google Scholar] [Crossref]

41. North, D. C. (1990). Institutions, institutional change and economic performance. Cambridge University Press. [Google Scholar] [Crossref]

42. Ochala, I. (2024). Political economy of PPP infrastructure projects in Nigeria: Challenges and prospects. African Journal of Economic and Management Studies, 15(2), 245-262. [Google Scholar] [Crossref]

43. Okebukola, P., Abdullahi, I., & Balogun, B. (2004). Private sector participation in infrastructure development in Nigeria. Lagos: Nigerian Economic Summit Group. [Google Scholar] [Crossref]

44. Okeke, C. (2010). Land acquisition and compensation in infrastructure projects in Nigeria. Journal of African Law, 54(2), 267-286. [Google Scholar] [Crossref]

45. Okoye, P. U., & Adebayo, A. A. (2021). Regulatory framework for public-private partnerships in Nigeria: An assessment. Journal of Sustainable Development Law and Policy, 12(1), 78-102. [Google Scholar] [Crossref]

46. Okudan, O., & Çevikbaş, M. (2022). Alternative dispute resolution selection framework to settle disputes in public-private partnership projects. Journal of Construction Engineering and Management, 148(9), 04022078. [Google Scholar] [Crossref]

47. Oluwafemi, S. (2022). Risk management failures in PPP road projects: Lessons from Lekki Toll Road concession. Nigerian Journal of Construction Management, 23(1), 45-62. [Google Scholar] [Crossref]

48. Opawole, A., Jagboro, G. O., Adegbembo, T. F., & Awodele, O. A. (2020). Analysis of critical success factors for public-private partnership infrastructure projects in Nigeria. Journal of Engineering, Design and Technology, 18(6), 1755-1778. [Google Scholar] [Crossref]

49. Osei-Kyei, R., & Chan, A. P. C. (2017). Review of studies on the critical success factors for public-private partnership projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335-1346. [Google Scholar] [Crossref]

50. Osei-Kyei, R., & Chan, A. P. C. (2021). Conflict management in public-private partnership projects. In International Best Practices of Public-Private Partnership (pp. 145-168). Springer. [Google Scholar] [Crossref]

51. Oyeyoade, S. F., & Araloyin, F. M. (2019). The influence of sustainability and green management concepts on educational facility performance in Nigeria. Real Estate Management and Valuation, 27(2), 77-96. [Google Scholar] [Crossref]

52. Oyeyoade, S. F., Ayorinde, O. I., & Oyewole, M. O. (2024). Utilizing dispute resolution mechanisms (DRMs) for conflict settlement in public-private partnership (PPP) education infrastructure development. Business Perspective Review, 6(1), 54-74. [Google Scholar] [Crossref]

53. Page, M. J., McKenzie, J. E., Bossuyt, P. M., et al. (2021). The PRISMA 2020 statement: An updated guideline for reporting systematic reviews. BMJ, 372, n71. [Google Scholar] [Crossref]

54. Patreli Partners. (2023). Nigeria's Arbitration and Mediation Act 2023: A practical guide. Lagos: Patreli Partners. [Google Scholar] [Crossref]

55. Powell, W. W., & DiMaggio, P. J. (Eds.). (1991). The new institutionalism in organizational analysis. University of Chicago Press. [Google Scholar] [Crossref]

56. Sanni, G. A., & Adebiyi, J. O. (2017). Dispute resolution in public private partnerships (PPPs) contracts in Nigeria. Nigerian Research Journal of Engineering and Environmental Sciences, 2(1), 259-269. [Google Scholar] [Crossref]

57. Scott, W. R. (2014). Institutions and organizations: Ideas, interests, and identities (4th ed.). SAGE Publications. [Google Scholar] [Crossref]

58. Sinha, A. K., & Jha, K. N. (2020). Dispute resolution and litigation in PPP road projects: Evidence from select cases. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 12(1), 05019007. [Google Scholar] [Crossref]

59. Siyaidon, J. (2022, July 4). Improving access to justice under new arbitration regime in Nigeria. The Guardian Online Newspaper. Retrieved from https://guardian.ng [Google Scholar] [Crossref]

60. Uwem, E., & Abubakar, Y. (2013). Public-private partnership and sustainable development of infrastructures in Nigeria. Advances in Management & Applied Economics, 3(6), 113-128. [Google Scholar] [Crossref]

61. Vanguard Newspapers Online. (2022, August 9). ASUU strike: FG's budgetary allocation to education lowest in 2022 - Report. Retrieved from https://www.vanguardngr.com [Google Scholar] [Crossref]

62. Williamson, O. E. (1985). The economic institutions of capitalism. Free Press. [Google Scholar] [Crossref]

63. Williamson, O. E. (1996). The mechanisms of governance. Oxford University Press. [Google Scholar] [Crossref]

64. World Bank. (2025). Dispute resolution mechanisms. World Bank PPP Knowledge Lab. Retrieved from https://ppp.worldbank.org [Google Scholar] [Crossref]

65. Yang, J., Shen, G. Q., Ho, M., Drew, D. S., & Chan, A. P. C. (2009). Exploring critical success factors for stakeholder management in construction projects. Journal of Civil Engineering and Management, 15(4), 337-348. [Google Scholar] [Crossref]

66. Yescombe, E. R. (2018). Public-private partnerships: Principles of policy and finance (2nd ed.). Oxford: Butterworth-Heinemann. [Google Scholar] [Crossref]

67. Zartman, I. W. (1989). Ripe for resolution: Conflict and intervention in Africa. Oxford University Press. [Google Scholar] [Crossref]

Metrics