Project Scope Management and Implementation Performance of Educational Infrastructure Stimulus Projects in Kenya: The Moderating Role of Human Capital
Authors
Dr. Kenneth Otieno Odhiambo, PhD
University of Nairobi, Faculty of Management Sciences, Department of Project Planning and Management (Kenya)
Article Information
Publication Timeline
Submitted: 2026-07-06
Accepted: 2026-07-16
Published: 2026-07-24
Abstract
This study examined the moderating influence of human capital on the relationship between project scope management and the implementation performance of Economic Stimulus Programme (ESP) infrastructure initiatives in public secondary schools within Kisumu County, Kenya. Utilizing a descriptive survey design, primary data were collected from a target population of 189 institutional stakeholders across schools benefiting from ESP allocations, yielding a finalized analytical sample of 128 respondents selected via stratified random sampling. Reliability was verified using the test-retest method and evaluated via the Spearman-Brown Prophecy formula (Re > 0.70). Data were analyzed using descriptive statistics, Chi-square tests of independence, and moderated multiple linear regression analysis. The empirical results revealed a strong overall model fit (R = 0.813, R2 = 0.661), indicating that 66.1% of the variance in infrastructure implementation status was driven by front-end project scope initialization metrics. Parameter estimates confirmed that formalized Project Charters (β = 0.394, p < 0.001) and inter-disciplinary Expert Judgment (β = 0.256, p = 0.006) exerted a statistically significant positive influence on delivery success. Crucially, individual Project Manager Competence failed to achieve direct statistical significance (β = 0.155, p = 0.065), demonstrating a condition of bounds-based moderation where individual capability depended entirely on structural institutional baselines. The study concluded that the Ministry of Education must transition from ad-hoc project selections toward mandatory, deliverable-oriented Work Breakdown Structures (WBS) and institutionalize technical scope management certification protocols for local oversight committees.
Keywords
Project Scope Management, Project Implementation, Economic Stimulus Programme (ESP)
Downloads
References
1. Adeyemi, A. O., & Amhana, P. (2024). Operational governance and scope creep in public infrastructure execution: A sub-Saharan perspective. International Journal of Project Management Studies, 16(2), 112–128. [Google Scholar] [Crossref]
2. Adeyemi, T., & Amhana, P. (2024). Fiscal interventions and educational infrastructure resilience: An assessment of Nigeria’s Economic Sustainability Plan. African Journal of Public Policy, 12(2), 45–61. [Google Scholar] [Crossref]
3. Aljadhai, S., Motala, T., & Siriram, R. (2024). Beyond the blueprints: Evaluating human capability constraints in decentralized public sector infrastructure delivery. Journal of Construction Engineering and Management, 150(4), 04024015. [Google Scholar] [Crossref]
4. Amoah, C., Nzuki, J. M., & Kithandi, J. (2024). Institutional friction and project management mechanics in decentralized educational infrastructure: A comparative study of Kenya and Ghana. African Development Review, 36(1), 45–59. [Google Scholar] [Crossref]
5. Amoah, K., Mensah, J., & Osei-Kofi, E. (2024). Harmonizing emergency stimulus with social policy: Evaluating the Ghana CARES ‘Obaatanpa’ programme in secondary education. Journal of Development Studies, 19(1), 112–129. [Google Scholar] [Crossref]
6. Andrews, M., Pritchett, L., & Woolcock, M. (2013). Escaping capability traps through problem driven iterative adaptation (PDIA). World Development, 48, 234–244. [Google Scholar] [Crossref]
7. Aschauer, D. A. (1989). Is public expenditure productive? Journal of Monetary Economics, 23(2), 177–200. [Google Scholar] [Crossref]
8. Bakkah, A. M. (2025). The stakeholder-scope nexus: Mitigating cognitive divergence in public sector asset delivery. Project Management Journal, 56(3), 201–216. [Google Scholar] [Crossref]
9. Banda, R. K., & Pretorius, L. (2016). The effect of front-end project scope planning on the performance of public infrastructure projects. South African Journal of Industrial Engineering, 27(4), 141–155. [Google Scholar] [Crossref]
10. Barney, J. (1991). Firm resources and sustained competitive advantage. Journal of Management, 17(1), 99–120. [Google Scholar] [Crossref]
11. Barro, R. J. (1990). Government spending in a simple model of endogenous growth. Journal of Political Economy, 98(5, Pt. 2), S103–S125. [Google Scholar] [Crossref]
12. Calderón, C., & Servén, L. (2010). Infrastructure and economic development in sub-Saharan Africa. Journal of African Economies, 19(Suppl. 1), i13–i87. [Google Scholar] [Crossref]
13. Crawford, L., Costello, K., Pollack, J., & Lopez, L. (2003). Soft skills and technical competencies: Managing expectations in decentralized project environments. International Journal of Project Management, 21(3), 203–211. [Google Scholar] [Crossref]
14. De Wit, A. (1988). Measurement of project success. International Journal of Project Management, 6(3), 164–170. [Google Scholar] [Crossref]
15. Fashina, A. A., Fakunle, F. F., & Opoku, A. (2020). Analyzing the key failure factors of construction projects in Africa: A systemic planning perspective. Journal of Engineering, Project, and Production Management, 10(2), 109–121. [Google Scholar] [Crossref]
16. Federal Government of Nigeria. (2020). The Nigeria economic sustainability plan (NESP). Federal Ministry of Finance, Budget and National Planning. [Google Scholar] [Crossref]
17. Flyvbjerg, B. (2013). Quality control and due diligence in project management: Getting decisions on public infrastructure right. International Journal of Forecasting, 29(4), 760–771. [Google Scholar] [Crossref]
18. Gacheru, E. N. (2015). Factors influencing completion of public school construction projects in Kenya (Doctoral dissertation, University of Nairobi). [Google Scholar] [Crossref]
19. Gibson, G. E. (2006). Pre-project planning: Principles, practices, and benefits. Journal of Construction Engineering and Management, 132(12), 1223–1231. [Google Scholar] [Crossref]
20. Githenya, M. S., & Ngugi, K. (2014). Assessment of the determinants of performance of housing construction projects in Kenya. International Journal of Social Sciences and Entrepreneurship, 1(11), 343–353. [Google Scholar] [Crossref]
21. Government of Kenya. (2009). Economic stimulus programme: Resuscitating the economy for sustainable growth. Government Printer. [Google Scholar] [Crossref]
22. Gwayo, A. O., Masau, S. M., & Wanyona, G. (2014). Analysis of the causes of project delays in the Kenyan construction industry. International Journal of Soft Computing and Engineering, 4(2), 223–231. [Google Scholar] [Crossref]
23. Hajialiasghari, M. (2021). Empirical modeling of project planning and scope definition on cost and schedule predictability. Construction Management and Economics, 39(8), 643–661. [Google Scholar] [Crossref]
24. Highsmith, J. (2009). Agile project management: Creating innovative products (2nd ed.). Addison-Wesley Professional. [Google Scholar] [Crossref]
25. Ika, L. A. (2012). Project management for information systems: A critique of traditional approaches in international development. Project Management Journal, 43(6), 65–80. [Google Scholar] [Crossref]
26. Ika, L. A. (2020). Why public sector projects fail in developing economies: A mixed-methods institutional assessment. World Development, 129, 104119. [Google Scholar] [Crossref]
27. Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). John Wiley & Sons. [Google Scholar] [Crossref]
28. Kipruto, K. J., & Muturi, W. (2014). Factors influencing financial performance of constituency development funded projects in Kenya. International Journal of Social Sciences and Entrepreneurship, 1(12), 390–405. [Google Scholar] [Crossref]
29. Kohli, U. (2001). Project management in public sector undertakings. Indian Journal of Public Administration, 47(3), 345–356. [Google Scholar] [Crossref]
30. Li, Y. (2022). Quantitative analysis of scope verification protocols and their impact on construction deviations. Journal of Management in Engineering, 38(5), 04022031. [Google Scholar] [Crossref]
31. Love, P. E. D., Edwards, D. J., & Irani, Z. (2012). Moving beyond optimism bias and strategic misrepresentation in construction projects. IEEE Transactions on Engineering Management, 59(4), 567–577. [Google Scholar] [Crossref]
32. Lucas, R. E. (1988). On the mechanics of economic development. Journal of Monetary Economics, 22(1), 3–42. [Google Scholar] [Crossref]
33. Mbaluku, J. M., & Bwisa, H. (2013). Factors influencing the execution of infrastructural projects in public universities in Kenya. International Journal of Academic Research in Business and Social Sciences, 3(8), 209–221. [Google Scholar] [Crossref]
34. McLean, S. (2022). Eradicating the infrastructure deficit: Fiscal packages and social equity in South African schools. Southern African Development Review, 26(3), 88–104. [Google Scholar] [Crossref]
35. Ministry of Education, Ghana. (2022). Free Senior High School monitoring and capacity report. Ministry of Education. [Google Scholar] [Crossref]
36. Ministry of Education, Kenya. (2021). Post-COVID-19 economic recovery strategy institutional guidelines for basic education infrastructure. Ministry of Education. [Google Scholar] [Crossref]
37. Mirzaei, A. (2019). Managing baseline changes under high technological uncertainty: The limits of formal scope verification. International Journal of Innovation and Technology Management, 16(3), 1950024. [Google Scholar] [Crossref]
38. Motala, S. (2024). Structural adjustments and constitutional mandates: The modernization of educational infrastructure in rural South Africa. Journal of Education Policy and Infrastructure, 31(1), 14–35. [Google Scholar] [Crossref]
39. Muchungu, P. K. (2012). The contribution of human factors to project performance in the building industry in Kenya (Doctoral dissertation, University of Nairobi). [Google Scholar] [Crossref]
40. Munamo, F. W. (2012). An analysis of completion rates of public sector civil engineering projects in Kenya (2010–2012). National Construction Authority. [Google Scholar] [Crossref]
41. Munns, A. K., & Bjeirmi, B. F. (1996). The role of project management in achieving project success. International Journal of Project Management, 14(2), 81–87. [Google Scholar] [Crossref]
42. Musa, J. A. (1999). An investigation into the factors causing delays in water infrastructure projects in Kenya (Unpublished master's thesis). University of Nairobi. [Google Scholar] [Crossref]
43. Namusonge, G. S., Kabare, K., & Mutua, S. (2012). Role of human capital configuration in organizational performance measures. International Journal of Academic Research in Business and Social Sciences, 2(11), 190–205. [Google Scholar] [Crossref]
44. National Treasury, South Africa. (2020). Supplementary budget review: COVID-19 fiscal response. National Treasury. [Google Scholar] [Crossref]
45. Newton, R. (2015). The project manager: Mastering the art of delivery (2nd ed.). Pearson. [Google Scholar] [Crossref]
46. Pinto, J. K., & Winch, G. M. (2022). Strategic misrepresentation, optimism bias, and project planning: Reconciling the behavioral and governance perspectives. International Journal of Project Management, 40(6), 621–633. [Google Scholar] [Crossref]
47. Project Management Institute. (2008). A guide to the project management body of knowledge (PMBOK® guide) (4th ed.). Project Management Institute. [Google Scholar] [Crossref]
48. Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK® guide) (5th ed.). Project Management Institute. [Google Scholar] [Crossref]
49. Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® guide) (7th ed.). Project Management Institute. [Google Scholar] [Crossref]
50. Serrador, P., & Pinto, J. K. (2015). Does Agile work? A quantitative analysis of agile project success. International Journal of Project Management, 33(5), 1040–1051. [Google Scholar] [Crossref]
51. Siriram, R. (2022). Project scope initiation frameworks and baseline stability in developing public infrastructure execution. IEEE Transactions on Engineering Management, 69(3), 745–758. [Google Scholar] [Crossref]
52. Talukhaba, A. A. (1988). Time and cost performance of construction projects in Kenya (Unpublished doctoral dissertation). University of Nairobi. [Google Scholar] [Crossref]
53. Thomas, H. R., & Napolitan, C. L. (1995). Quantitative effects of construction changes on labor productivity. Journal of Construction Engineering and Management, 121(3), 290–296. [Google Scholar] [Crossref]
54. Turner, J. R. (2019). The handbook of project-based management: Leading strategic change in organizations (5th ed.). McGraw-Hill Education. [Google Scholar] [Crossref]
55. Voetsch, R. J., Cioffi, D. F., & Anbari, F. T. (2004). Project risk management practices and their relationship to project success. Project Management Journal, 35(1), 33–47. [Google Scholar] [Crossref]
56. Williams, T. (2019). The front-end of projects: A systematic review and research agenda. International Journal of Project Management, 37(3), 364–379. [Google Scholar] [Crossref]
Metrics
Views & Downloads
Similar Articles
- Ayurveda and Skin Health: A Comprehensive Framework for the Management of Dermatological Disorders
- Gender and Political Exclusion: An Analysis of Women's Marginalization in India's Democracy
- Safety Standards Compliance among Universities Employees in Nairobi County, Kenya During the Covid-19 Pandemic
- Cedi Appreciation Relative to Fuel Prices - A Machine Learning and Ancient Geomantic Approach