Cash-Flow Implementation and the Delivery of Public Infrastructure Projects: Evidence from the Uganda National Roads Authority, Uganda

Authors

Geoffrey Karyeija

Universal Technology and Management University (Uganda)

Dr. J. M. O. Tukei

Uganda Universal Technology and Management University (Uganda)

C. D. Alupo

Uganda Revenue Authority (Uganda)

L. Tukei

Capital Markets Authority (Uganda)

E. R. Ayait

Uganda Police Force (Uganda)

Article Information

DOI: 10.47772/IJRISS.2026.101100165

Subject Category: Project Management

Volume/Issue: 10/11 | Page No: 2441-2457

Publication Timeline

Submitted: 2026-10-15

Accepted: 2026-10-20

Published: 2026-11-21

Abstract

Public infrastructure delivery depends not merely on the approval of budgets but on the effectiveness with which approved financial resources are translated into actual, timely and accountable expenditure. A project may have an approved budget, signed contract and technically feasible work programme yet remain operationally constrained when fund releases, procurement commitments, payment certificates and contractor payments are delayed or inconsistently executed. This article examined the relationship between cash-flow implementation and the delivery of public infrastructure projects at the Uganda National Roads Authority (UNRA).
The study was derived from a convergent mixed-methods investigation involving 78 questionnaire respondents, 10 key informants and documentary evidence from ten substantially completed road-infrastructure projects. Quantitative data were analysed using descriptive statistics, Pearson's correlation and simple linear regression, while qualitative and documentary evidence were thematically interpreted to explain the observed statistical relationships.
The findings revealed that respondents generally recognised the existence of formal policies governing fund release and expenditure approval. However, concerns emerged regarding procurement transparency, predictability of funding, merit-based allocation, timely approval of financial obligations and prompt payment of contractors, suppliers and service providers. Documentary evidence further demonstrated considerable time extensions and cost escalation associated with delayed disbursement, delayed approval of interim payment certificates, land-acquisition constraints, reallocation of project funds, scope changes and interest on overdue payments. Cash-flow implementation had a positive and statistically significant relationship with public infrastructure-project implementation (r = .536, p < .01). Regression analysis further demonstrated that cash-flow implementation significantly predicted infrastructure-project implementation (β = .536, p < .001), accounting for 28.7% of the observed variance in project-performance outcomes (R² = .287).
The study concludes that public infrastructure performance depends substantially on the effectiveness of financial execution rather than budget approval alone. Timely fund release, credible commitment control, transparent procurement, efficient payment-certification systems, protection of approved project resources and predictable contractor payments are therefore essential for reducing avoidable project delays, financing costs and implementation disruption. The article recommends stronger integration of financial and physical-progress monitoring, electronic tracking of payment processes, improved accountability for payment delays and greater alignment between public-sector cash releases and contractual implementation requirements.

Keywords

cash-flow implementation; public infrastructure; project delivery; fund disbursement; contractor payment; public financial management; UNRA; Uganda

Downloads

References

1. Chadee, A., Ali, H., Gallage, S., & Rathnayake, U. (2023). Modelling the implications of delayed payments on contractors' cashflows on infrastructure projects. Civil Engineering Journal, 9(1), 52–71. https://doi.org/10.28991/CEJ-2023-09-01-05 [Google Scholar] [Crossref]

2. Creswell, J. W., & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed.). SAGE Publications. [Google Scholar] [Crossref]

3. Ggoobi, R., Lukwago, D., & Bogere, G. (2020). Public expenditure governance in the roads sector. Advocates Coalition for Development and Environment. [Google Scholar] [Crossref]

4. Ika, L. A., & Pinto, J. K. (2022). The “re-meaning” of project success: Updating and recalibrating for modern project management. International Journal of Project Management, 40(7), 835–848. https://doi.org/10.1016/j.ijproman.2022.08.001 [Google Scholar] [Crossref]

5. International Monetary Fund. (2022). Uganda: Technical report—Public investment management assessment. IMF Staff Country Reports, 2022(350). https://doi.org/10.5089/9798400224867.002 [Google Scholar] [Crossref]

6. Muzaale, T., & Auriacombe, C. J. (2018). Policy challenges to road infrastructure projects performance: Trends, issues and concerns in Uganda. African Journal of Public Affairs, 10(3), 134–154. [Google Scholar] [Crossref]

7. Nawaf, M. A.-N. (2022). The effect of cash flow variation on project performance: An empirical study from Kuwait. The Journal of Asian Finance, Economics and Business, 9(3), 53–63. https://doi.org/10.13106/jafeb.2022.vol9.no3.0053 [Google Scholar] [Crossref]

8. Nguyen, V. T., Do, S. T., Tran, C. N. N., & Vo, M. D. (2024). Assessing the impact of the traits of payment delay causes on subcontractor's business performance in construction projects: A case study in Vietnam. International Journal of Construction Management, 24(11), 1259–1269. https://doi.org/10.1080/15623599.2022.2152980 [Google Scholar] [Crossref]

9. Ochary, J. (2016). Factors influencing time and cost overruns on construction projects in Uganda [Unpublished master's thesis]. Islamic University in Uganda. [Google Scholar] [Crossref]

10. Omag, A. (2016). Cash flows from financing activities: Evidence from the automotive industry. International Journal of Academic Research in Accounting, Finance and Management Sciences, 6(1), 115–122. [Google Scholar] [Crossref]

11. Public Finance Management Act, 2015. (2015). Uganda Printing and Publishing Corporation. [Google Scholar] [Crossref]

12. Tripathi, A., & Gardner, J. (2016). Strengthening cash management. International Monetary Fund. [Google Scholar] [Crossref]

13. Uganda National Roads Authority. (2020). UNRA corporate strategic plan 2020/21–2024/25. UNRA. [Google Scholar] [Crossref]

14. Uganda National Roads Authority. (2021/2022). Annual performance report. UNRA. [Google Scholar] [Crossref]

15. Uganda National Roads Authority. (2022). Project status report. UNRA. [Google Scholar] [Crossref]

16. Zohrabi, M. (2013). Mixed method research: Instruments, validity, reliability and reporting findings. Theory and Practice in Language Studies, 3(2), 254–262. https://doi.org/10.4304/tpls.3.2.254-262 [Google Scholar] [Crossref]