Empirical Influence of Social Acceptance Risks on the Performance of Public-Private Partnership Renewable Energy Projects in Kenya

Authors

Dr. Kenneth Otieno Odhiambo

PhD, University of Nairobi, Faculty of Management Sciences, Department of Project Planning and Management (Kenya)

Article Information

DOI: 10.47772/IJRISS.2026.100700567

Subject Category: Education

Volume/Issue: 10/7 | Page No: 8264-8277

Publication Timeline

Submitted: 2026-07-23

Accepted: 2026-07-28

Published: 2026-08-07

Abstract

Public-private partnerships (PPPs) are widely considered a prudent response to the problem of limited public funding in energy infrastructure development. However, social acceptance risks represent a major inhibiting factor that negatively affects the performance and subsequent financing of renewable energy projects. This study investigated how social acceptance risks influence the performance of PPP renewable energy projects in Kenya, focusing specifically on geothermal energy projects. Guided by a pragmatic paradigm, the study employed a mixed-methods approach incorporating both correlational and descriptive survey research designs. Quantitative data was collected using a self-administered questionnaire, while qualitative data was gathered via an interview guide. From a target population of 769 relevant employees at the Kenya Electricity Generating Company Limited (KenGen), a sample size of 263 respondents was determined using the Yamane formula. Descriptive analysis utilized mean scores and standard deviations, while inferential analysis employed Pearson's Product-Moment Correlation (r) and linear regression modeling, with F-tests for hypothesis testing. Out of 263 distributed questionnaires, 207 were completed and returned, representing a 78.7% response rate. The regression model revealed that social acceptance risks exert a statistically significant influence on the performance of PPP renewable energy projects, F(1, 205) = 96.135, p < 0.001, accounting for 31.9% of the variance (R² = 0.319). The study therefore rejected the null hypothesis in favor of the alternative hypothesis, concluding that higher social acceptance risks significantly degrade project performance. Key risk sub-factors such as inadequate community participation, low project awareness, environmental pollution concerns, and unresolved land compensation issues were identified as negative drivers. The study recommends robust public participation, participatory planning frameworks, and transparent stakeholder engagement strategies during the project formulation and implementation phases to cushion renewable energy PPPs from social acceptance shocks.

Keywords

Social acceptance risks, Project financing, Public-Private Partnerships (PPP), Geothermal Renewable Energy, Stakeholder theory.

Downloads

References

1. Agterbosch, S., Meertens, R. M., & Vermeulen, W. J. V. (2009). The relative importance of social and institutional conditions in the planning of wind power projects. Renewable and Sustainable Energy Reviews, 13(2), 393–405. https://doi.org/10.1016/j.rser.2007.10.010 [Google Scholar] [Crossref]

2. Aitken, M. (2010). Why we still don’t understand the social aspects of wind power: A critique of key assumptions within the literature. Energy Policy, 38(4), 1834–1841. https://doi.org/10.1016/j.enpol.2009.11.060 [Google Scholar] [Crossref]

3. Akrofi, M. M., & Okitasari, M. (2022). Integrating energy access and climate shift goals in Africa: Assessing the constraints of utility-scale renewable deployment. Energy Policy, 168, Article 113117. https://doi.org/10.1016/j.enpol.2022.113117 [Google Scholar] [Crossref]

4. Akrofi, M. M., & Okyere, S. A. (2022). Towards a sustainable energy transition in Africa: Reviewing the land-energy-water nexus of utility-scale solar and wind energy projects. Energy Research & Social Science, 88, Article 102521. https://doi.org/10.1016/j.erss.2022.102521 [Google Scholar] [Crossref]

5. Arap-Ruto, J. (2021). Socio-economic impacts of geothermal energy development on indigenous communities: A case study of the Olkaria geothermal power project in Naivasha, Kenya. African Journal of Environmental Science and Technology, 15(4), 145–158. https://doi.org/10.5897/AJEST2020.2941 [Google Scholar] [Crossref]

6. Babatunde, S. O., Perera, S., Zhou, L., & Udeaja, C. (2021). Barriers to public-private partnership implementation in developing countries: A comparative study. Journal of Engineering, Design and Technology, 19(5), 1122–1144. https://doi.org/10.1108/JEDT-04-2020-0114 [Google Scholar] [Crossref]

7. Badi, S. M., & Pryke, S. (2017). Assessing the impact of risk allocation on sustainable energy innovation: The case of private finance initiative school projects. International Journal of Managing Projects in Business, 9(2), 282–308. [Google Scholar] [Crossref]

8. Batel, S. (2020). Research on the social acceptance of renewable energy technologies: Critical review and a further research agenda. Frontiers in Psychology, 11, Article 560710. https://doi.org/10.3389/fpsyg.2020.560710 [Google Scholar] [Crossref]

9. Batinić, N. (2021). Sovereign guarantees and contract structural resilience in public-private partnerships: The true shield against localized operational vulnerabilities. Journal of Financial Management of Property and Construction, 26(3), 301–319. https://doi.org/10.1108/JFMPC-02-2020-0009 [Google Scholar] [Crossref]

10. Casady, C. B., Cepparulo, A., & Giuriato, L. (2024). Public-private partnerships for low-carbon, climate-resilient infrastructure: Insights from the literature. Journal of Cleaner Production, 470, 143338. https://doi.org/10.1016/j.jclepro.2024.143338 Cited by: 113 [Google Scholar] [Crossref]

11. Dengerink, J. (2011). Experiences with renewable energy in Uganda: A participatory evaluation of the Uganda Domestic Biogas Programme (Master’s thesis, University of Amsterdam, Netherlands). [Google Scholar] [Crossref]

12. Devine-Wright, P. (2014). Dynamics of place attachment in a climate changed world: From personal protection to collective action. In L. C. Manzo & P. Devine-Wright (Eds.), Place attachment: Advances in theory, methods and applications (pp. 165–177). Routledge. [Google Scholar] [Crossref]

13. Eberhard, A., Gratwick, K., Morella, E., & Stenzel, P. (2018). Independent power projects in Sub-Saharan Africa: Lessons from five key countries. World Bank Research Observer, 33(1), 1–45. https://doi.org/10.1093/wbro/lkx005 [Google Scholar] [Crossref]

14. Evans, B., Parks, J., & Theobald, K. (2011). Urban wind power and the private sector: Community benefits and public engagement. Journal of Environmental Planning and Management, 54(2), 227–244. https://doi.org/10.1080/09640568.2010.505829 [Google Scholar] [Crossref]

15. Evenhuis, E., & Vickerman, R. (2010). Transport pricing and public-private partnerships in theory: Issues and suggestions. Research in Transportation Economics, 30(1), 6–14. [Google Scholar] [Crossref]

16. Ferguson-Martin, C. J., & Hill, S. D. (2011). Accounting for variation in wind deployment between Canadian provinces. Energy Policy, 39(3), 1647–1658. https://doi.org/10.1016/j.enpol.2010.12.040 [Google Scholar] [Crossref]

17. Fielmua, N. (2011). The role of the community ownership and management strategy towards sustainable access to water in Ghana. Journal of Sustainable Development, 4(3), 174–184. [Google Scholar] [Crossref]

18. Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview. Project Management Journal, 45(2), 6–19. https://doi.org/10.1002/pmj.21409 [Google Scholar] [Crossref]

19. Freeman, R. E. (1984). Strategic management: A stakeholder approach. Pitman. [Google Scholar] [Crossref]

20. Freeman, R. E., Harrison, J. S., Wicks, A. C., Parmar, B. L., & De Colle, S. (2010). Stakeholder theory: The state of the art. Cambridge University Press. [Google Scholar] [Crossref]

21. Gormally, A. M., Pooley, C. G., Whyatt, J. D., & Timmis, R. J. (2014). “They made gunpowder…yes down by the river there, that’s your energy source”: Attitudes towards community renewable energy in Cumbria. Local Environment, 19(8), 915–932. https://doi.org/10.1080/13549839.2013.810200 [Google Scholar] [Crossref]

22. Harris, F. (2010). A historical overview of stakeholder management. In E. Chinyio (Ed.), Construction stakeholder management (pp. 41–55). Blackwell Publishing. [Google Scholar] [Crossref]

23. Iossa, E., Spagnolo, G., & Vellez, M. (2007). Contract design in public-private partnerships. World Bank. [Google Scholar] [Crossref]

24. Jensen, M. C. (2001). Value maximization, stakeholder theory, and the corporate objective function. Journal of Applied Corporate Finance, 14(3), 8–21. https://doi.org/10.1111/j.1745-6622.2001.tb00434.x [Google Scholar] [Crossref]

25. Kamese, G. (2004). Renewable energy technologies in Uganda: The potential for geothermal energy development. AFREPREN. [Google Scholar] [Crossref]

26. Kang, C. C., Feng, C. M., & Kuo, C. Y. (2011). A royalty negotiation model for BOT projects: The operational revenue-based model. Mathematical and Computer Modelling, 54(9–10), 2338–2347. [Google Scholar] [Crossref]

27. Kilaka, M., & Omwega, J. (2015). Factors affecting the performance of public-private partnerships in infrastructure financing in Kenya: A case of Kenya Urban Roads Authority. International Journal of Social Sciences Management and Entrepreneurship, 2(1), 157–170. [Google Scholar] [Crossref]

28. Koissaba, B. R. (2018). Geothermal energy footprint on indigenous peoples’ land and livelihoods: A case study of the Olkaria geothermal power plants in Naivasha, Kenya. Land Use Policy, 79, 742–753. https://doi.org/10.1016/j.landusepol.2018.09.011 [Google Scholar] [Crossref]

29. Komendantova, N., & Battaglini, A. (2019). Beyond NIMBYism: Community acceptance of renewable energy infrastructure projects in developing contexts. Energy Policy, 129, 709–721. https://doi.org/10.1016/j.enpol.2019.02.056 [Google Scholar] [Crossref]

30. Lemaire, X., & Price, H. (2017). Best practices for public-private partnerships in renewable energy projects in Africa: The case of Kinangop Wind Park. Journal of Cleaner Production, 142(4), 2145–2156. https://doi.org/10.1016/j.jclepro.2016.11.088 [Google Scholar] [Crossref]

31. Loring, J. M. (2007). Wind energy planning in England, Wales and Denmark: Factors influencing project success. Energy Policy, 35(4), 2648–2660. [Google Scholar] [Crossref]

32. Malini, E. (1999). Build-operate-transfer municipal bridge projects in India. Journal of Management in Engineering, 15(4), 51–58. [Google Scholar] [Crossref]

33. Mariita, N. O. (2020). The impact of geothermal exploitation on land use and local communities in the Kenyan Rift Valley. Geothermal Energy Science, 8(1), 45–59. https://doi.org/10.5194/gtes-8-45-2020 [Google Scholar] [Crossref]

34. Ménard, C. (2012). Is public-private partnership obsolete? Assessing the obstacles and shortcomings of PPP. In P. de Vries & E. B. Yehoue (Eds.), The Routledge companion to public-private partnerships (pp. 149–174). Routledge. [Google Scholar] [Crossref]

35. Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega infrastructure projects: A review and future directions. International Journal of Project Management, 33(2), 446–457. https://doi.org/10.1016/j.ijproman.2014.08.007 [Google Scholar] [Crossref]

36. Muok, R. O., Ong’iro, A. O., & Kirai, P. (2021). Socio-technical barriers to the adoption of grid-connected renewable energy in rural Kenya. African Journal of Science, Technology, Innovation and Development, 13(5), 589–601. https://doi.org/10.1080/20421338.2020.1797290 [Google Scholar] [Crossref]

37. Muriithi, P. M., & Kwena, R. (2023). Determinants of public-private partnership project performance in the energy sector in Kenya: A case of Kenya Electricity Generating Company. International Journal of Project Management and Innovation, 7(2), 88–104. [Google Scholar] [Crossref]

38. Neuhoff, K., Sambalino, F., & Twesigye, P. (2018). Multi-level governance and the deployment of renewable energy in East Africa. Energy Policy, 121, 332–343. https://doi.org/10.1016/j.enpol.2018.06.035 [Google Scholar] [Crossref]

39. Newcombe, R. (2003). From client to project stakeholders: A stakeholder mapping approach. Construction Management and Economics, 21(8), 841–848. [Google Scholar] [Crossref]

40. Ng, A., Wong, J., & Wong, K. (2012). Institutional framework for managing social risks in public-private partnerships. International Journal of Project Management, 30(5), 540–551. https://doi.org/10.1016/j.ijproman.2011.10.003 [Google Scholar] [Crossref]

41. Ng, S. T., Wong, J. M., & Wong, K. K. (2019). A dynamic social license to operate framework for infrastructure procurement under public-private partnerships. Built Environment Project and Asset Management, 9(2), 214–228. https://doi.org/10.1108/BEPAM-03-2018-0058 [Google Scholar] [Crossref]

42. Osei-Kyei, R., & Chan, A. P. C. (2015). Review of studies on the critical success factors for public-private partnership projects. International Journal of Project Management, 33(6), 1335–1346. https://doi.org/10.1016/j.ijproman.2015.02.008 [Google Scholar] [Crossref]

43. Osei-Kyei, R., & Chan, A. P. C. (2017). Empirical comparison of critical success factors for public-private partnerships in developing and developed economies. Journal of Facilities Management, 15(2), 122–145. https://doi.org/10.1108/JFM-07-2016-0032 [Google Scholar] [Crossref]

44. Otieno, G. O., & Awiti, A. O. (2020). Information asymmetry, community education status, and the public acceptance of clean energy infrastructures in rural Kenya. Renewable and Sustainable Energy Reviews, 124, Article 109789. https://doi.org/10.1016/j.rser.2020.109789 [Google Scholar] [Crossref]

45. Patterson, D., & Pun, L. (2015). A value management approach for managing social project risks of international funding discontinuity in Guyana. The West Indian Journal of Engineering, 38(1), 79–85. [Google Scholar] [Crossref]

46. Power Africa. (2017). Annual report 2017. USAID. [Google Scholar] [Crossref]

47. Private Participation in Infrastructure Database. (2017). World Bank Group. http://ppi.worldbank.org/ [Google Scholar] [Crossref]

48. Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK® guide) (5th ed.). Project Management Institute. [Google Scholar] [Crossref]

49. Rod, J. (2011). Social consent for large onshore wind energy projects (Master’s thesis, Harvard University). [Google Scholar] [Crossref]

50. Rybach, L. (2003). Geothermal energy: Sustainability and the environment. Geothermics, 32(4–6), 463–470. [Google Scholar] [Crossref]

51. Schilling, J., Locham, R., & Scheffran, J. (2018). Winds of change or wind of conflicts? Community perceptions of the Lake Turkana Wind Power Project in Kenya. Land, 7(2), Article 48. https://doi.org/10.3390/land7020048 [Google Scholar] [Crossref]

52. Schilling, M. A., & Esmundo, M. (2009). Technology S-curves in renewable energy alternatives: Analysis and implications for industry and government. Energy Policy, 37(5), 1767–1781. [Google Scholar] [Crossref]

53. Sovacool, B. K., Ali, S. H., Bazilian, M., Radley, B., Nemery, B., Okatz, J., & Ramana, M. V. (2020). Sustainable minerals and metals for a low-carbon future. Science, 367(6473), 30–33. https://doi.org/10.1126/science.aaz6003 [Google Scholar] [Crossref]

54. Sovacool, B. K., Lema, A., & Hamborg, S. (2023). The socio-political dynamics of green mega-projects: Social acceptance, land acquisition, and resistance in East African renewable energy corridors. World Development, 161, Article 106114. https://doi.org/10.1016/j.worlddev.2022.106114 [Google Scholar] [Crossref]

55. Spackman, M. (2002). Public-private partnerships: Lessons from the British approach. Economic Systems, 26(3), 283–301. https://doi.org/10.1016/S0939-3625(02)00048-1 [Google Scholar] [Crossref]

56. Wekesa, S. N., & Ngugi, L. (2025). Operational bottlenecks and non-technical risk management frameworks within Kenya’s Vision 2030 energy infrastructure pipeline. East African Journal of Engineering and Technology, 8(1), 12–29. [Google Scholar] [Crossref]

57. Williamson, O. E. (1998). The institutions of governance. The American Economic Review, 88(2), 75–79. [Google Scholar] [Crossref]

58. Winch, G. M. (2001). Governing the project process: A transaction cost economics approach. Construction Management and Economics, 19(8), 799–808. https://doi.org/10.1080/01446190110086311 [Google Scholar] [Crossref]

59. Wüstenhagen, R., Wolsink, M., & Bürer, M. J. (2007). Social acceptance of renewable energy innovation: An introduction to the concept. Energy Policy, 35(5), 2683–2691. https://doi.org/10.1016/j.enpol.2006.12.001 [Google Scholar] [Crossref]

60. Yuan, J., Li, W., Guo, J., Zhao, X., & Skibniewski, M. J. (2018). Social risk factors of transportation PPP projects in China: A sustainable development perspective. International Journal of Environmental Research and Public Health, 15(7), Article 1323. [Google Scholar] [Crossref]

61. Zhao, X., Hwang, B. G., & Yu, G. S. (2021). Identifying critical risks of public-private partnership renewable energy projects. Sustainability, 13(6), Article 3171. https://doi.org/10.3390/su13063171 [Google Scholar] [Crossref]