Understanding Technical Conflict Drivers and Management of Construction of Public Water Works Projects in Uganda

Authors

Wesigomwe Jamil Mohammed ORCID icon for Wesigomwe Jamil Mohammed

Kabale University, P. O. Box 317, Kabale, Uganda (Uganda)

Prof. Sabiti Makara

Kabale University, P. O. Box 317, Kabale, Uganda (Uganda)

Assoc. Prof. Mesharch Katusiimeh

Kabale University, P. O. Box 317, Kabale, Uganda (Uganda)

Assoc. Prof. Lawrence Muhwezi

Kabale University, P. O. Box 317, Kabale, Uganda (Uganda)

Article Information

DOI: 10.47772/IJRISS.2026.100500071

Subject Category: Public Administration

Volume/Issue: 10/5 | Page No: 1038-1052

Publication Timeline

Submitted: 2026-04-23

Accepted: 2026-04-29

Published: 2026-05-23

Abstract

This research investigated the effect of technical conflict drivers on management of construction of public water works projects in Victoria, Albertine and Kyoga water management zones (WMZs) of eastern and southwestern regional centers of Uganda’s water sector. A positivist paradigm underpinned the research where a cross-sectional design was applied. The population that was involved in this research was 690 from which 468 were simple randomly selected but 448 actually participated in this research. The Advanced Analysis of covariance (ADANCO) was used to analyze data where a Structural Equation Modeling (SEM) accompanied with Bootstrapping was performed to produce results that included measurement loadings, path coefficient and coefficient of determination. Key findings were drawing interpretations were the most causal factor of technical conflicts, followed by quality and workmanship, design changes, technical experience and design errors. There was a negative path coefficient (-0.827) between technical conflict causes and management of construction of public water works projects. Drawing interpretations were the most technical conflict cause that severely undermined management of construction of public water works projects, followed by quality and workmanship, design changes, technical experience and design errors.

Keywords

Technical Conflict Drivers, Management of Construction and Public Water Works Projects

Downloads

References

1. Achyut, N. (2021). Transaction cost theory and hydropower project finance in Nepal. National Judicial Academy (NJA) Law Journal, 205-216 [Google Scholar] [Crossref]

2. Adetayo, O. A. (2025). Understanding Cronbach’s alpha in social and management studies. Current Science Research Bulletin, 2(2), 11-16. [Google Scholar] [Crossref]

3. Alaloul, W. S., Hasaniyah, M. W. & Tayeh, B. A. (2019). A Comprehensive Review of Disputes Prevention and Resolution in Construction Projects. In MATEC web of conferences (Vol. 270, p. 05012). EDP Sciences. [Google Scholar] [Crossref]

4. Alsulamy, S. (2022). Investigating critical failure drivers of construction project at planning stage in Saudi Arabia. Frontiers in Engineering and Built Environment, 2(3), 154-166. [Google Scholar] [Crossref]

5. Azar, A. D., Militaru, C. & Mattar, C. P. (2018). Construction design-phase errors and their impacts on project performance case study of Lebanese local applications. International Journal of Engineering and Information Systems (IJEAIS), 2(7), 42-46. [Google Scholar] [Crossref]

6. Budget Monitoring and Accountability Unit, Ministry of Finance, Planning and Economic Development (2025). Natural resources, environment, climate change, land and water resources management programme. Annual Monitoring Report Financial Year 2024/25. Kampala: Ministry of Finance, Planning and Economic Development [Google Scholar] [Crossref]

7. Cheah, J-H., Memon, M. A. & Chuah, F. (2018). Assessing reflective models in marketing research: a comparison between PLS AND PLSc estimates. International Journal of Business and Society, 19(1), 139-160. [Google Scholar] [Crossref]

8. Cuypers, I. R. P., Hennart, J-F. & Silverman, B. S. (2021). Transaction cost theory: Past progress, current challenges and suggestions for the future. Academy of Management Annals, 12(1), 111-150. [Google Scholar] [Crossref]

9. Dos Santos, P. M. & Cirillo, M. A. (2021). Construction of the average variance extracted index for construct validation in structural equation models with adaptive regressions. Mathematics, Statistics & Data Science, 52(4), 1639-1650. [Google Scholar] [Crossref]

10. Durand, A. (2019). How to prevent disputes in construction contracts due to cultural. PM World Journal, 8(9) 1-16. [Google Scholar] [Crossref]

11. Elgeddawy, M. & Abouraia, M. (2024). Pragmatism as a research paradigm. European Conference on Research Methodology for Business and Management Studies, 23(1), 71-74. doi: [Google Scholar] [Crossref]

12. 34190/ecrm.23.1.2444 [Google Scholar] [Crossref]

13. Fatawu, A., Adamu, I, Sidik, M. A. & Fortunatus, M. (2020). Assessing the factors that cause poor quality of design and contract documentation and the influence on project implementation in Ghana. Civil and Environmental Research, 12(7), 70-83. doi: 10.7176/CER/12-7-08 [Google Scholar] [Crossref]

14. Fredikind, T. (2022). Transaction Cost Economics as a Contributing Theory to Supply Chain Management: An Assessment and Application on Theoretical Basis. 3rd IBA Bachelor Thesis Conference, July 03rd, 2022, Enschede, The Netherlands. [Google Scholar] [Crossref]

15. Gamage, A. N. K. K. & Kumar, S. (2024a). An empirical study on the effects of disputes on successful completion of construction projects. Scholars Journal of Engineering and Technology, 89-100. doi: 10.36347/sjet.2024.v12i02.007 [Google Scholar] [Crossref]

16. Ikediashi, D. I., Ogunlana, S. O. & Alotaibi, A. (2022). Analysis of project failure factors for infrastructure projects in Saudi Arabia: A multivariate approach. Journal of Construction in Developing Countries, 19(1), 35-52. [Google Scholar] [Crossref]

17. International Finance Corporation (IFC, 2013). Public-Private Partnership Impact Stories - Uganda: Small Scale Infrastructure Provider Water Program. Retrieved from [Google Scholar] [Crossref]

18. https://www.ifc.org/content/dam/ifc/doc/2010/2013-uganda-water-ppp-brief.pdf [Google Scholar] [Crossref]

19. Jaffar, N., Tharim, A. H. A. & Shuib, M. N. (2022). Factors of conflict in construction industry: A literature review. Procedia Engineering, 20, 193-202. [Google Scholar] [Crossref]

20. Kaushik, V. & Walsh, C. A. (2019). Pragmatism as a research paradigm and its implications for social work research. Social Sciences, 8(9), 255, 1-17. doi.org/10.3390/socsci 8090255 [Google Scholar] [Crossref]

21. Ketokivi, M. & Mahoney, J. T. (2015). Transaction cost economics as a constructive stakeholder theory. Academy of Management Learning and Education, 15(1), 123-138. Doi: [Google Scholar] [Crossref]

22. 5465/amle.2015.0133 [Google Scholar] [Crossref]

23. Ketokivi, M. & Mahoney, J. T. (2015). Transaction cost economics as a constructive stakeholder theory. Academy of Management Learning and Education, 15(1), 123-138. Doi: [Google Scholar] [Crossref]

24. 5465/amle.2015.0133 [Google Scholar] [Crossref]

25. Kiilu, S. (2021). Causes and impacts of conflicts in construction projects: A viewpoint of Kenya construction industry. International Journal of Soft Computing and Engineering, 10(5), 1-8. doi: 10.35940/ijsce.D3485.0510521 [Google Scholar] [Crossref]

26. Kiiza, M. & Kityamuweesi, R. (2025). Community based water management system and sustainability of water sources in Western Albertine Region of Uganda. International Journal of Academic Multidisciplinary Research (IJAMR), 9(7), 197-206. [Google Scholar] [Crossref]

27. Koc, K. & Gurgun, A. P. (2021). Ambiguity factors in construction contracts entailing conflicts. Engineering Construction & Architectural Management, 29(9), 3895-3914. [Google Scholar] [Crossref]

28. Ministry of Finance, Planning and Economic Development (MOFPED, 2025). Performance of Externally Funded Projects (December 2024 - May 2025) Report. Kampala: MOFPED. [Google Scholar] [Crossref]

29. Ministry of Water and Environment (2018). Integrated Water Management and DevelopmentProject-P163782: Environmental and Social Management Framework-ESMF. Kampala: Ministry of Water and Environment. [Google Scholar] [Crossref]

30. Ministry of Water and Environment (2024). Integrated Water Management and Development Project-P163782: Environmental and Social Management Framework-ESMF. Kampala: Ministry of Water and Environment. [Google Scholar] [Crossref]

31. Ministry of Water and Environment (MWE, 2017). Water and Environment Sector Performance Report 2017. Kampala: Ministry of Water and Environment. [Google Scholar] [Crossref]

32. Ministry of Water and Environment (MWE, 2022). Environment and Social Impact Assessment (ESIA) for the Kiryandongo-Nyakabale project. Integrated Water Management Development Project. Kampala: Ministry of Water and Environment. [Google Scholar] [Crossref]

33. Ministry of Water and Environment (MWE, 2025a). Uganda Water Management and Development Project (WMDP) / Integrated Water Management and Development Project (IWMDP) Documentation. Kampala: Ministry of Water and Environment. [Google Scholar] [Crossref]

34. Ministry of Water and Environment (MWE, 2025b). Water and Environment: Ministerial Policy Statement Financial Year 2024/2025. Kampala: Ministry of Water and Environment. [Google Scholar] [Crossref]

35. Mitropoulos, P. & Howell, G. (2018). Model for Understanding, Preventing and Resolving Project Disputes. Journal of Construction Engineering and Management, 223-231. [Google Scholar] [Crossref]

36. Muhamad, N. H. & Mohammad, M. F. (2018). Impact of design changes in construction project. Malaysian Journal of Sustainable Environment, 1-18. [Google Scholar] [Crossref]

37. Olowolayemo, O. E., Opeyemi, S. W., Oluwatunmise, Olotu, F. M. & Oyegoke, I. K. (2024). Design error: Its effects on building projects delivery period. International Journal of Science and Research Archive, 12(01), 2376-2380. [Google Scholar] [Crossref]

38. Redouan, A. (2025). An empirical research using PLS-SEM to investigate the relationship between service quality dimensions, emotional and behavioral consumers in the banking sector. Futurity Economics & Law, 5(1), 98-117. [Google Scholar] [Crossref]

39. Salooma, A. & Khodeir, L. M. (2016). Analysis Of Root Causes Of Conflicts in Construction Projects In The Middle East. Conference Paper. [Google Scholar] [Crossref]

40. Sanni, A. O., Bello, W. A., Adu, E. T. & Ojo. S. M. (2024). Factors contributing to construction disputes in Nigerian public universities. Journal of Environmental Sciences (JOES), 23(1), 175-182. [Google Scholar] [Crossref]

41. Shamsudeen, M. (2016). Effects of design errors on construction projects. International Journal of Scientific and Engineering Research, 7(2), 1099-1114. [Google Scholar] [Crossref]

42. Silva, P. M., Domingo, N. & Ali, N. A. N. A. (2023). Causes of disputes in the construction industry - A systematic literature review. Journal of Financial Management of Property and Construction, 29(2), 193–210. [Google Scholar] [Crossref]

43. Wescoat, J., Koshul, B. & Muhammad, A. (2025). Principled pragmatism in water resources research: An historical and philosophical perspective on studies in South Asia and beyond. Water Resources Research, 61(12), 1-20. doi: 10.1029/2025WR040155 [Google Scholar] [Crossref]

44. Williamson, O. E. (2025). Transaction Cost Economics. In Ménard, C. and Shirley, M. M. (eds), Handbook of New Institutional Economics. Springer, Cham. https://doi.org/10 .1007/978-3-031-50810-3_4 [Google Scholar] [Crossref]

45. Yogen, M. (2022). The impact of design errors on construction project performance. Journal of Civil Engineering and Management, 20(6), 746-759. [Google Scholar] [Crossref]