Survival Strategies for Construction Companies in Sarawak, Malaysia amidst Challenging Economic Climate

  • Chu Sheng Ding
  • Joan Tze Shan Chua
  • Prescilla Anak Palis
  • Chih Siong Wong
  • Shi Yee Wong
  • Angela Mee Yii Ting
  • 1655-1671
  • Jul 11, 2024
  • Business Administration

Survival Strategies for Construction Companies in Sarawak, Malaysia amidst Challenging Economic Climate

Chu Sheng Ding*, Joan Tze Shan Chua, Prescilla Anak Palis, Chih Siong Wong, Shi Yee Wong, Angela Mee Yii Ting 

School of Built Environment, University of Technology Sarawak, 96000 Sibu, Sarawak, Malaysia

*Corresponding Author

DOI: https://dx.doi.org/10.47772/IJRISS.2024.806124

Received: 07 June 2024; Accepted: 13 June 2024; Published: 11 July 2024

ABSTRACT

The emergence of Covid-19 pandemic had caused a major economic downturn worldwide especially in early 2020. During that period of time, many construction companies were forced to deal with the impacts by adopting various strategies to ensure their existence and further development. Although the Covid-19 health emergency was declared ended in 2023, there are still many challenges ahead the road to economic recovery. In Malaysia, the economic outlook in 2024 is still uncertain due to global economic uncertainty driven by Russia-Ukrain conflicts and Middle East conflicts, skilled labour shortage, and supply chain disruptions in other countries. In this uncertain environment, the construction industry should pre-plan strategies to cope with future challenging economic climate. Through literature review, it was discovered that there is a lack of studies in Sarawak, Malaysia on how the construction companies should respond to the negative economic impacts. Therefore, this paper aims to study the survival strategies of construction companies in Sarawak amidst challenging economic climate. A quantitative research approach was adopted in order to achieve the aim. Structured questionnaires were distributed to Grade 7 construction companies in Sarawak for them to rate the importance of 53 survival strategies based on a 5-point Likert scale. The received 130 valid responses were analyzed using descriptive statistics and RII methods. The findings show that the most important survival strategies are “implementing stricter site management to reduce material & time wastage in order to achieve lowest construction cost”, “carefully considering the payment terms and the client ability to make payment”, and “implementing stricter financial management on company cash flow” while the least important strategies are “diversifying into non-construction related businesses”, “increasing staff working hours”, and “converting permanent staff into temporary placements”. The findings of the present research could serve as a guideline to the construction companies in Sarawak to address the challenges posed by the economic crisis. Besides, the present research is also useful to researchers or academicians who intend to conduct more research on this topic.

Keywords: Survival Strategies, Construction Companies, Challenging Economy

INTRODUCTION

In early 2020, Covid-19 pandemic had negatively disrupted all countries and had caused a major economic downturn (Norhaidin & Tan, 2023; Toh et al. 2023). The pandemic is unprecedented. Its impacts on economy is the greatest since the Great Recession in 2008. The challenging economy had affected many sectors including the construction industry (Lagat et al., 2023; Mohamed & Kamaruding, 2023). In Malaysia, Q1 2020 to Q4 2021 had been highlighted by the Department of Statistics Malaysia (DOSH) as a recession period (DOSH, 2020, 2021). During the challenging period, the Malaysian construction companies faced numerous impacts, including material shortage, cost escalation, labour shortage, decrease in revenue, limited projects and demands, suspension of projects, and financial difficulties (Esa et al., 2020; Gamil & Alhagar, 2020; Norhaidin & Tan, 2023; Tan, 2021; Toh, 2020; Zamani et al., 2021).

The Malaysian economy started to recover since year 2022. However, the economy will not grow forever uninterruptedly. Based on the economic/business cycle theory, when the economy reach the peak, it will undergo a downturn (Figure 1).

Business cycle theory

Figure 1: Business cycle theory (Ezeanyeji et al., 2019)

Besides, the economic outlook of Malaysia in 2024 is still uncertain due to some challenges, such as global economic uncertainty driven by Russia-Ukrain conflicts and Middle East conflicts, skilled labour shortage and and supply chain disruptions in other countries (Liew, 2024). Therefore, the construction industry should still pre-plan strategies to cope with future challenging economic climate. According to Mohamed and Kamaruding (2023), the construction companies should manage their survival strategies for their long term business run and to avoid problematic situations. Besides, Toh et al. (2023) also opined that if there is no strategies in place, construction companies may face “uphill battle to remain viable” during the post Covid-19 environment. Similarly, Abubakar et al. (2022) stated that strategic planning is essential for construction companies to survive in volatile environment.

Several research (Adegbembo et al., 2020; Aghimien et al., 2018; Buys & Rooyen, 2014; Lagat et al., 2024; Lim et al., 2010; Ruddock et al., 2014; Scott, 2011; Zuo et al., 2015)) have been conducted worldwide to study the survival strategies that the construction industry had adopted during the economic downturn. However, there is a lack of research which focus on the Malaysian context. To the best of the authors’ knowledge, there is only three research being conducted in Malaysia namely, by Bakar et al. (2011) who studied the survival strategies applied by Grade 7 construction companies in West Malaysia during the two periods of recession in the 1980s and 1990s, by Norhaidin and Tan (2023) who studied the survival strategies applied by eighteen Grade 4 to Grade 7 construction companies in Malaysia, and by Toh et al. (2023) who studied the strategies for small and medium construction companies in Klang Valley. Although Norhaidin and Tan (2023) had covered a wider scope of study, the sample size for the study is small (only 18 questionnaires were analyzed). To date, a comprehensive research which specifically focuses on Sarawak, Malaysia has yet to be conducted. Therefore, this paper aims to study the survival strategies of construction companies in Sarawak, Malaysia amidst challenging economic climate. In order to meet the aim, two objectives have been set: (i) to identify survival strategies for Grade 7 constuction coampnies in Sarawak amidst challenging economic climate and (ii) to prioritize survival strategies for Grade 7 construction companies in Sarawak amidst challenging economic climate. Grade 7 construction companiess were targetted because they are of the highest grade registered under CIDB and therefore hold a decisive position in the Sarawak construction industry in determining the performance and growth of the industry. The research process and findings are explained in this paper.

LITERATURE REVIEW

Impacts of Challenging Economic Climate to the Construction Companies

Literature shows that economic impacts can be interrelated. The disruption of material transportation can cause material shortages and also an increase in material costs (Esa et al., 2020; Gamil & Alhagar, 2020; Lagat et al., 2023; Mohamed & Kamaruding, 2023; Zamani et al., 2021). As a result, the total construction cost would increase, thus increasing the construction companies’ financial pressure (Jayalath, 2023). Unexpected closure and projects suspension cause progress delays, creating inflation risks and additional financial charges to the construction companies (Al-Keim, 2017; Lagat et al., 2023). Due to the lack of projects initiated in the industry, the intense market competition increases the difficulties in winning jobs and correspondingly decrease the company’s revenue and business turnover (Aghimien et al., 2018; Ogbu, 2017; Olowa et al., 2018). The above impacts create financial burden which is the main impact to the construction company. Without effective strategies to improve the company’s financial capabilities and ensure proper cash flow, the company’s survival would be threatened (Tansey et al., 2013). Kam et al. (2022) and Lagat et al. (2023) opined that construction practitioners should consider survival measures to “remain afloat” or “alive”. Thus, it is necessary to study the survival strategies that could be adopted by the construction companies in a challenging economic environment.

Survival Strategies Adopted by Construction Companies in a Challenging Economy

Survival strategies refer to the tactics adopted to weather the storms of economic and deal with the impacts effectively during the turbulent economic situation (Aghimien et al., 2018; Tansey et al., 2013; Ye et al., 2010). Based on extensive literature review, 53 survival strategies were identified and subsequently categorized into six main categories, as shown in Table 1. The six categories are strategies related to human resources management, financial management, project bidding, diversification, networking, and business model and management.

Table 1: Survival Strategies Adopted by construction companies amidst challenging economy climate

Source

                                           Survival Strategy

Abubakar et al. (2022) Adewuyi & Otali (2017) Aghimien et al. (2018) Al-Tobi & Manchiryal (2020) Bakar et al. (2011) Bhagatkar et al. (2015) Buys & Rooyen (2014) Jayalath (2023) Lim et al. (2010) Norhaidin & Tan (2023) Olowa et al. (2018) Ruddock et al. (2014) Scott (2011) Tansey et al. (2013) Toh et al. (2023) Zuo et al. (2015)
A Strategies related to Human Resources Management
SHRM1 Staff layoff/downsizing
SHRM2 Reducing or freezing staff recruitment
SHRM3 Reducing or freezing staff salaries/increment/allowance/bonuses
SHRM4 Employing more experienced staff members
SHRM5 Employing staff/foreign professionals on a project by project/contract basis
SHRM6 Employing cost claim consultants in order to increase revenue
SHRM7 Converting permanent employees into temporary placements
SHRM8 Staff training, upskill and multi-tasking
SHRM9 Flexible working arrangements
SHRM 10 Increasing staff working hours
SHRM 11 Practicing effective communication with staff and management
B Strategies related to Financial Management
SFM1 Implementing stricter financial management on company cash flow
SFM2 Implementing stricter site management to reduce material & time wastage in order to achieve lowest construction cost
SFM3 Cutting cost e.g., operational/administrative cost, supplier cost, R&D budget
SFM4 Reducing cost incurred on contract dispute through contract management
SFM5 Creating contingency funds from company reserves
SFM6 Negotiating for alternative loan services with the financial institutes
SFM7 Entering into security agreements with project owners and financial institutes
SFM8 New financing arrangements with clients
SFM9 Rescheduling or eliminating debt
SFM10 Utilizing surplus funds in financial investment
SFM11 Investing into R&D to further explore business opportunities
C Strategies related to Project Bidding
SPB1 Bidding for more projects that are within the firm resources and capabilities
SPB2 Bidding for projects with lower or zero profit margin
SPB3 Quoting reasonable and affordable fees and prices in bids
SPB4 Undertaking short-term, fast track as well as smaller contract/project
SPB5 Setting limits on project size so that any failure of one project would not endanger the firm’s operation
SPB6 Carefully considering the payment terms and the client ability to make payment
D Strategies related to Diversification
SD1 Diversifying into construction related business (e.g. sale or lease of construction materials and equipment)
SD2 Diversifying into non-construction related businesses (e.g. manufacturing of automobile or household products)
SD3 Market Penetration (e.g. into emerging or foreign market)
SD4 Tendering on different type of project e.g., residential, commercial, industrial
E Strategies related to Networking
SN1 Focusing on forming and improving relationship with stakeholders, clients, contractors, suppliers
SN2 Collaborative partnerships with clients, contractors, suppliers, architects
SN3 Adopting merger and acquisition with construction companies
SN4 Forming Joint Venture with other construction companies
F Strategies related to Business Models and Management
SBMM1 Concentrating on core business that the company familiar with
SBMM2 Change in geographical location (business & staff)
SBMM3 Implementing stricter procurement procedures
SBMM4 Strategic resources acquisition and realignment such as construction materials and equipment
SBMM5 Increasing and improving delivery quality and standards
SBMM6 Adopting new technologies/innovations
SBMM7 Practicing effective marketing strategies
SBMM8 Improving organisational culture with practices such as laying emphasis on goals and tasks accomplishment
SBMM9 Improving and adapting organizational structure
SBMM

10

Servicing only a specific group of clients
SBMM

11

Subcontracting work from other construction companies
SBMM

12

Introducing sustainability initiatives
SBMM

13

Maintaining socially responsible practices to create company image
SBMM

14

Reverting to simple efficiency planning
SBMM

15

Reviewing project risks and invest in risk management
SBMM

16

Reducing turnover rate (Number of business/project)
SBMM

17

Reviewing health and safety measures continuously to reduce accidents

Strategies related to Human Resources Management

Human resources management strategies can be adopted to manage the employment costs and enhance the workforce’s and company’s capabilities to create some means of competitive edge over their counterparts (Aghimien et al., 2018).

During an economic downturn, construction demands may decline, thereby causing the workforce exceeds the company’s needs (Olowa et al., 2018). Therefore, the construction companies who participated in previous research suggested to adopt staff layoff/downsizing to get rid of unnecessary workforce and reduce or freeze staff recruitment to avoid the additional employment cost (Adewuyi & Otali, 2017; Aghimien et al., 2018; Al-Tobi & Manchiryal, 2020; Bhagatkar et al., 2015; Lim et al., 2010; Scott, 2011; Buys & Rooyen, 2014; Olowa et al., 2018; Zuo et al., 2015). Bhagatkar et al. (2015) revealed that it is easier to reduce operating costs than to generate additional revenue. If staff layoff strategy is adopted, construction companies tend to increase working hours of the remaining staff to compensate for the reduction in workforce so as to maintain business operations (Tansey et al., 2013).

In the intense competition environment, it is vital to preserve the company’s long-run competitiveness. It was revealed that increasing the workforce’s abilities through staff training and multi-tasking can assist in building a company’s competitive advantage (Aghimien et al., 2018; Lagat et al., 2023; Ruddock et al., 2014; Tansey et al., 2013; Zuo et al., 2015). On the other hand, some construction companies also inclined to recruit foreign professionals and experienced workforce who require lower pay on a contract basis in order to minimize the employment and training costs (Lim et al., 2010; Tansey et al., 2013; Zuo et al., 2015).

Besides, practising effective communication with staff and management gives chances to the team to contribute to the company and discuss measures to address the economic challenges (Adewuyi & Otali, 2017). Scott (2011) mentioned that it is important to let the employees know that their jobs are still secure, although the situation is severe.

Strategies related to Financial Management

Economic downturns may cause insolvency of construction companies due to cash flow issues and financial difficulties (Edmund et al., 2018; Tansey et al., 2013). Therefore, construction companies should focus on financial management in order to survive. Previous research revealed that implementing stricter financial management such as dropping off low/zero profit items from the production line, amending the purchasing rules and conducting project milestone monitoring system are effective in controlling cash flow (Al-Tobi & Manchiryal, 2020; Aghimien et al., 2018; Lim et al., 2010; Ruddock et al., 2014; Ogbu, 2017; Scott, 2011; Tansey et al., 2013). Since the project profit margin is tight during the downturn, the construction companies may seek ways to reduce the construction cost and the impacts of material cost inflation (Al-Keim, 2017; Yuan, 2013). In order to achieve the lowest construction cost, stricter site management can be implemented to reduce material and time wastage, improve project performance and create positive impacts on the company’s cash flow (Al-Tobi & Manchiryal, 2020; Lim et al., 2010; Scott, 2011; Ruddock et al., 2014).

Another challenge caused by difficult economic situation is shortage of capital. To cope with this challenge, construction comapnies may cut supplier costs to switch the limited capital to the more essential areas (Olowa et al., 2018; Tansey et al., 2013). Aside from cost-cutting, Lim et al. (2010) stated that preparing sufficient contingency funds can help minimize the impacts on the company’s operations.

In the case of prolonged recession, some construction companies also chose to negotiate for alternative loan services with financial institutions to relief their burden (Adewuyi & Otali, 2017; Lim et al., 2010; Olowa et al., 2018; Tansey et al., 2013). Besides, in order to avoid contract disputes which may cause additional expenses, practising proper contract management, entering into new financing and security agreements with clients and financial institutions can be adopted (Aghimien et al., 2018; Lim et al., 2010; Tansey et al., 2013).

Strategies related to Project Bidding

In a challenging economic environment, construction companies tend to avoid bidding for large-scale projects beyond their capability (Lim et al., 2010). This is because over-trading of work and overstretching of resources and capabilities may trigger self-destruction if the construction companies lose control of the project and correspondingly intensify the economic impacts (Lim et al., 2010; Zuo et al., 2015).

Besides, the main source of profit for construction companies is the profit margin that is added onto the price of contracts at the bidding stage. Thus, Scott (2011) discovered that the construction companies would quote a reasonable and affordable price at the bidding stage to generate revenue. However, clients will generally award the contract to the lowest bid. Therefore, in order to maintain the company cash flow and retain their staff, most of the construction companies were willing to bid for projects with lower or zero profit margin to win more projects although the economic condition is severe (Adewuyi & Otali, 2017; Lim et al., 2010; Zuo et al., 2015). Mitigations such as lowering projects material and operational expenses are needed to reduce the impacts of lower profit margin (Lim et al., 2010).

In addition, construction companies also tend to undertake contracts that can be completed within a short period, such as factory and industrial building projects, to increase their turnover and improve cash flow (Lim et al., 2010; Olowa et al., 2018). Furthermore, before bidding a project and entering into a contract, the construction companies should carefully consider the payment terms and the client’s financial capability to avoid payment issues (Ruddock et al., 2014).

Strategies related to Diversification

In a challenging economic environment, the number of projects may reduce. Consequently, the construction companies’ revenue and turnover would be affected significantly, thereby threatening their survival (Aghimien et al., 2018; Ogbu, 2017; Ruddock et al., 2014). Therefore, the construction companies may tender for different types of project and penetrate into emerging or overseas markets which have high construction service demands (Adewuyi & Otali, 2017; Al-Tobi & Manchiryal, 2020; Bakar et al., 2011; Bhagatkar et al., 2015; Lim et al., 2010; Olowa et al., 2018; Scott, 2011; Zuo et al., 2015).

Diversification into construction related business (sales or lease of construction materials and equipment) or non-construction related business (manufacturing automobile and household products) may help reduce the impacts faced by the companies (Adewuyi & Otali, 2017; Aghimien et al., 2018; Al-Tobi & Manchiryal, 2020; Bhagatkar et al., 2015; Buys & Rooyen, 2014; Lim et al., 2010; Olowa et al., 2018; Scott, 2011; Tansey et al., 2013; Zuo et al., 2015). By practising these strategies, the companies can expand their business to create an additional income stream, establish companies’ position in the competitive market, enhance the company’s capabilities, and enrich the services delivered to the clients (Aghimien et al., 2018; Lim et al., 2010; Olowa et al., 2018).

Strategies related to Networking

Practicising collaborative partnerships and developing a strong relationship with other construction companies is an important factor to increase a company’s competitiveness (Lim et al., 2010; Zuo et al., 2015). Some benefits of these strategies include increased company’s reach, increased jobs of different fields, reduced issues and conflicts between parties, and improved productivity and profitability (Adewuyi & Otali, 2017; Aghimien et al., 2018; Lim et al., 2010; Olowa et al., 2018; Ruddock et al., 2014; Scott, 2011; Zuo et al., 2015).

Through merger and acquisition or forming joint ownership, two or more companies can combine their resources and technology to establish a new entity that possesses a greater value (Bhagatkar et al., 2015). It could help achieve growth and expand business through synergies to gain a strategic position in the competitive market. Construction companies could secure large scale projects by relying on the expertise of their partners as well as by sharing profit and risk (Bhagatkar et al., 2015; Lim et al., 2010; Olowa et al., 2018; Tansey et al., 2013; Zuo et al., 2015).

Strategies related to Business Models and Management

Zuo et al. (2015) discovered that in the challenging economic environment, construction companies that do not revise their business models have a higher possibility of suffering from negative impacts. Therefore, business operating models and management need to be reviewed and revised from time to time to cope with the changes in the market and industry.

There is a risk of loss of revenue when entering into an unfamiliar market during a recession (Zuo et al., 2015). Olowa et al. (2018) and Tansey et al. (2013) mentioned that it is more beneficial for construction companies who have insufficient capabilities and resources in managing other businesses to focus on the core business areas to rebuild their strength. Besides, construction companies should continuously review health and safety measures to prevent accidents that may create unpredicted expenses and invest in risk management to identify, analyze, and respond effectively to any possible risk that may arise in a project (Ruddock et al., 2014).

By implementing stricter procurement procedures, the potential team players and supply chain capabilities should be considered during the selection stage to avoid issues and conflict that may create additional expenses and exarcebate the construction company’s financial burden (Bhagatkar et al., 2015; Lim et al., 2010; Ruddock et al., 2014; Tansey et al., 2013). In addition, implementing a central procurement system to consolidate and order the materials in bulk quantity can help reduce the purchasing cost and avoid capital and time wastage caused by poor cost estimating (Lim et al., 2010). Apart from that, strategic resources acquisition and realignment enables effective utilization of the current and essential construction materials and equipment among the projects, thus reducing the impacts of the cost escalation (Aghimien et al., 2018; Bakar et al., 2011; Buys & Rooyen, 2014; Lim et al., 2010).

In order to strengthen market position during challenging times, the service and products provided must be of a valuable and superior quality that the clients desire. Therefore, improving quality and standards by adopting new technologies/innovations and practising effective marketing strategies have been focused to create company’s reputation and branding, retain existing clients and attract collaboration with new customers during the challenging period (Adewuyi & Otali, 2017; Aghimien et al., 2018; Bakar et al., 2011; Bhagatkar et al., 2015; Olowa et al., 2018; Ruddock et al., 2014; Scott, 2011; Tansey et al., 2013).

RESEARCH METHODOLOGY

This study adopted a quantitative approach in order to reach construction companies that are geographically dispersed and to enhance research generalizabiliy (Creswell & Creswell, 2018). Besides, this method also allowed the authors to gather data within a short duration (Apuke, 2017). In line with the previous similar research conducted by Bakar et al. (2011), the targetted respondents for this study is the Grade 7 construction companies in Sarawak registered under Construction Industry Development Board (CIDB). This was because Grade 7 construction companies are classified the highest grade under CIDB and they play an important role in determining the performance and growth of the industry. They have more chances to involve in large projects and possess more workforces. Thus, the impacts caused by the challenging economic climate would be more significant to them.

A simple random sampling method was adopted to select the research sample. This was due to the need to avoid bias so that every individual in the population has equal chances to be selected and the results will be more reliable to represent the whole population (Fellows & Liu, 2015). Structured self-administered survey questionnaires were distributed to 259 construction companies through email as well as delivered by the authors in person. Each set of questionnaire consisted of Section A (Respondent’s General Information) and Section B (Level of Importance of the Survival Strategies). Under Section B, the respondents were invited to rate the survival strategies based on a five-point Likert scale where 1 = Very Unimportant, 2 = Unimportant, 3 = Moderately Important, 4 = Important, and 5 = Very Important.

The data collected were analyzed using SPSS Descriptive statistics to calculate the mean value and standard deviation of each survival strategy. Besides, Relative importance index (RII) method was used to prioritize the survival strategies. RII is considered a statistical method that can be used to determine the ranking of the variables (Hossen et al., 2015).

FINDINGS AND DISCUSSIONS

In the present study, a total of 86 responses out of 259 questionnaires distributed were received (33.2% response rate). According to Aghimien et al. (2018) and Sekaran and Bougie (2016), the study will be reliable if the response rate achieves at least 20% to 30%.

Table 2: Job designations of respondents

Job Position Frequency Percentage (%)
Managing director 16 18.6
Project director 10 11.6
General director 7 8.1
Project/Site engineer 4 4.7
Contract manager 3 3.5
Project/Construction manager 4 4.7
Site superintending/Supervisor 7 8.1
Others 35 40.7

As shown in Table 2, among the 86 respondents who participated in the present study, 33 of them are from the director level, which consists of 16 managing directors (18.6%), 10 project directors (11.6%), and 7 general directors (8.1%). Moreover, 18 of them are management superiors, including 4 project/site engineers (4.7%), 3 contract managers (3.5%), 4 project/construction managers (4.7%), and 7 site superintendents/supervisors (8.1%). The majority of respondents under the “others” category (40.7%) are quantity surveyors.

Table 3: Respondents’ Experience

Years of Experience Frequency Percentage (%)
Less than 5 years 31 36.0
6-10 years 18 20.9
11-15 years 8 9.3
16-20 years 12 14.0
More than 20 years 17 19.8

As shown in Table 3, 36% of the respondents possess less than five years of working experience, followed by 20.9% of them had six to ten years of working experience. Besides, 9.3% had 11 to 15 years of working experience, 14% had 16 to 20 years of experience, and 19.8% of respondents who had more than 20 years of working experience.

Table 4: Geographical location of the respondents

Location Frequency Percentage (%)
Kuching 51 59.3
Samarahan 2 2.3
Sri Aman 1 1.2
Sarikei 2 2.3
Sibu 10 11.6
Bintulu 10 11.6
Miri 10 11.6

As shown in Table 4, most responses were collected from Kuching (59.3%). There are 11.6% of responses collected from Sibu, Bintulu, and Miri, respectively.

Figure 2: Type of company, type of project commonly involved in, company’s main work and business, and Company size

As shown in Figure 2, 96.5% of the respondents are from local companies while 3.5% are from joint venture companies. In terms of the type of project that the respondent or company is commonly involved in, 79.1% of respondents were commonly involved in public projects whereas 70.9% commonly involved in private projects. There is only 2.3% of the respondents involved in foreign projects.

Besides, regarding the company’s main work and business, most of the respondents took part in civil engineering works (76.7%) and building works (68.6%). In the present study, company size is determined by the current number of employees in the company. Based on the data collected, 51.2% of companies recruited 11-50 employees, 18.6% of Grade 7 construction companies employed more than 100 employees, 16.3% of companies employed less than 10 employees and 14% of them had 50-100 employees.

Descriptive Statistics and Relative Importance Index of the survival strategies

Based on the results shown in Table 5, there are 33 important survival strategies and 19 moderately important strategies that can be adopted by the companies in the Sarawak construction industry. However, there is one unimportant survival strategy among 53 strategies in the present study.

Table 5: Rankings of survival strategies that can be adopted by construction companies in a challenging economic environment

Category Variables Mean Standard Deviation RII value Ranking Remarks
SFM2 Implementing stricter site management to reduce material & time wastage in order to achieve lowest construction cost 4.2907 0.7494 0.8581 1 Important
SPB6 Carefully considering the payment terms and the client ability to make payment 4.1860 0.8191 0.8372 2 Important
SFM1 Implementing stricter financial management on company cash flow 4.1047 0.7826 0.8209 3 Important
SBMM1 Concentrating on core business that the company familiar with 4.0465 0.7957 0.8093 4 Important
SPB1 Bidding for more projects that are within the company resources and capabilities 4.0233 0.9328 0.8047 5 Important
SBMM5 Increasing and improving project delivery quality and standards 3.9767 0.7967 0.7953 6 Important
SHRM11 Practicing effective communication with staff and management 3.9535 0.9192 0.7907 7 Important
SN1 Focusing on forming and improving relationship with stakeholders, clients, contractors, suppliers etc. 3.9535 0.8528 0.7907 8 Important
SPB3 Quoting reasonable and affordable fees and prices in bids 3.9302 0.7482 0.7860 9 Important
SN2 Collaborative partnerships with clients, contractors, suppliers, architects etc. 3.8372 0.9057 0.7674 10 Important
SBMM9 Improving and adapting organizational structure 3.8140 0.8333 0.7628 11 Important
SBMM4 Strategic resources acquisition and realignment (e.g., leasing rather than buying the less utilized equipment, use resources more efficiently based on the cost-effectiveness) 3.7907 0.8277 0.7581 12 Important
SBMM15 Reviewing project risks and invest in risk management 3.7907 0.8693 0.7581 13 Important
SBMM6 Adopting new technologies/innovations in business to differentiate from other companies 3.7791 0.9629 0.7558 14 Important
SPB5 Setting limits on project size so that any failure of one project would not endanger the firm’s operation 3.7674 0.8633 0.7535 15 Important
SFM9 Rescheduling or eliminating debt 3.7558 0.9572 0.7512 16 Important
SBMM3 Implementing stricter procurement procedures in terms of supply chain selection and material purchasing method 3.7558 0.8108 0.7512 17 Important
SBMM8 Improving organizational culture with practices such as laying emphasis on goals and tasks accomplishment 3.7209 0.8765 0.7442 18 Important
SBMM17 Reviewing health and safety measures continuously to reduce accidents 3.7209 0.9286 0.7442 19 Important
SFM5 Creating contingency funds from company reserves 3.7093 0.9186 0.7419 20 Important
SHRM5 Employing staff/foreign professionals on a project by project/contract basis 3.6744 0.9132 0.7349 21 Important
SD4 Tendering on different type of work e.g., residential, commercial, industrial 3.6395 0.9811 0.7279 22 Important
SFM6 Negotiating for alternative loan services with the financial institutes 3.6279 0.9462 0.7256 23 Important
SBMM14 Reverting to simple efficiency planning 3.6163 0.8834 0.7233 24 Important
SFM10 Utilizing surplus funds in financial investment 3.6047 0.9366 0.7209 25 Important
SPB4 Undertaking short-term, fast track as well as smaller contract/project 3.6047 0.9111 0.7209 26 Important
SHRM8 Staff training, upskill and multi-tasking 3.5930 0.9378 0.7186 27 Important
SFM4 Reducing cost incurred on contract dispute through contract management 3.5814 0.9996 0.7163 28 Important
SFM3 Cutting cost e.g., operational/administrative cost, supplier cost, R&D budget 3.5698 0.9272 0.7140 29 Important
SFM8 New financing arrangements with clients 3.5698 1.0005 0.7140 30 Important
SBMM7 Practicing effective marketing strategies (e.g., advertisement hoardings, telemarketing, participation in property expo) 3.5465 0.9781 0.7093 31 Important
SHRM4 Employing more experienced staff members 3.5349 1.1029 0.7070 32 Important
SHRM9 Flexible working arrangements 3.5233 1.0817 0.7047 33 Important
SBMM11 Subcontracting work from other construction companies 3.4884 0.9791 0.6977 34 Moderately Important
SD1 Diversifying into construction related business (e.g., renovation, sale or lease of construction materials and equipment, mechanical & electrical work) 3.4651 1.0023 0.6930 35 Moderately Important
SFM7 Entering into security agreements with project owners and financial institutes 3.4419 0.9531 0.6884 36 Moderately Important
SBMM13 Maintaining socially responsible practices to create company image 3.4070 0.9986 0.6814 37 Moderately Important
SBMM12 Introducing sustainability initiatives (e.g., measurement of energy consumption of project) 3.3488 0.9913 0.6698 38 Moderately Important
SBMM16 Reducing turnover (Number of business/project) 3.3372 0.9531 0.6674 39 Moderately Important
SHRM2 Reducing or freezing staff recruitment 3.3256 0.9755 0.6651 40 Moderately Important
SN3 Adopting merger and acquisition with construction companies 3.2558 0.9602 0.6512 41 Moderately Important
SFM11 Investing into R&D to further explore business opportunities 3.2093 0.8827 0.6419 42 Moderately Important
SN4 Forming joint venture with other construction companies 3.2093 0.9836 0.6419 43 Moderately Important
SHRM1 Staff layoff/downsizing 3.1977 0.9800 0.6395 44 Moderately Important
SBMM10 Servicing only a specific group of clients 3.1628 0.9562 0.6326 45 Moderately Important
SHRM3 Reducing or freezing staff salaries/increment/allowance/bonuses 3.0930 1.0586 0.6186 46 Moderately Important
SPB2 Bidding for projects with lower profit margin 3.0698 0.9304 0.6140 47 Moderately Important
SBMM2 Change in geographical location (business & staff) 3.0698 1.0932 0.6140 48 Moderately Important
SHRM6 Employing cost claim consultants in order to increase revenue 2.9070 1.1128 0.5814 49 Moderately Important
SD3 Market Penetration (e.g., into emerging or foreign market) 2.8605 1.1289 0.5721 50 Moderately Important
SD2 Diversifying into non-construction related businesses (e.g., manufacturing of automobile or household products, operation of the hospitality industry) 2.8256 1.0649 0.5651 51 Moderately Important
SHRM10 Increasing staff working hours 2.6744 0.9993 0.5349 52 Moderately Important
SHRM7 Converting permanent staff into temporary placements 2.4884 0.9042 0.4977 53 Unimportant

(Note for mean value: 1.0-1.49= very unimportant, 1.5-2.49= unimportant, 2.5-3.49= moderately important, 3.5-4.49= important, 4.5-5.0= very important)

Top three survival strategies

Based on Table 5, “implementing stricter site management to reduce material and time wastage in order to achieve lowest construction cost” is ranked the 1st (RII 0.8581). This finding is consistent with the previous studies done in Malaysia by Norhaidin and Tan (2023), Singapore by Lim et al. (2010), and New Zealand by Scott (2011), where this strategy was ranked as No.1, No. 1, and No. 2, respectively. According, Lim et al. (2010) and Scott (2011), stricter site management is critical and the company recognised the need to be more proactive in site management when the profit margin is tight during economic downturn. Through this strategy, material wastage can be minimized, the usability of the material can be maximized, and the performance of the project will be improved as well as provide a positive impact on the company’s cash flow (Ajayi et al., 2017; Al-Tobi & Manchiryal, 2020). Besides, construction company’s risk of incurring additional expenses would be lowered by avoiding any prematurely ordered material and ensure proper on-site storage (Al-Hajj & Hamani, 2011; Yuan, 2013). According to Zain et al. (2018), poor site management would lead to project delays.

“Carefully considering the payment terms and the client ability to make payment” is ranked the second with a mean value of 4.19 and standard deviation of 0.82. In the research conducted by Ruddock et al. (2014), this strategy had been voted as a top-five action undertaken by the UK construction companies during the economic downturn. This is because the clients may face financial difficulties and therefore not be able to make payment to the construction company. Late payment/non payment may bring negatively impacts to construction companies such as exacerbated financial burden, project suspension, and even insolvency (Akinsiku & Ajayi, 2016). Thus, before bidding or tendering a project, the financial ability of the clients should be carefully considered as this may help protect the construction companies against payment issues caused by the client.

“Implementing stricter financial management on company cash flow” is ranked the third with a mean value of 4.10 and a standard deviation of 0.78. This finding is consistent with the previous studies, as shown in Table 6. All of the researchers revealed that this strategy is essential in ensuring company’s survival during the challenging economy.

Table 6: Comparison of ranking between the previous and the present studies

Source Abubakar et al. (2022) Lim et al. (2010) Norhaidin & Tan (2023) Ruddock et al. (2014) Scott (2011) Toh et al. (2023) Present study
Ranking 2 1 2 1 2 1 3

Without proper financial management, the company’s financial difficulties may be intensified and thereby tightening the business profit margin (Mutti & Hughes, 2002; Naveed, 2020). Thus, “implementing stricter financial management on company cash flow” is perceived to be a key strategy to ensure company survival. It allows for precise spending tracking, enables the decision-maker to make a better financial decision based on the financial data and plans, and helps reduce any needless expenditures during the harsh period.

Bottom three survival strategies

“Diversifying into non-construction related business” is “moderately important” and ranked the 51st with a mean value of 2.83 a high standard deviation of 1.06. This finding is similar with the research conducted in Singapore by Lim et al. (2010), New Zealand by Scott (2011), and South Africa by Buys and Rooyen (2014). This finding could be due to lack of capital for expansion and lack of knowledge about the nature of non-construction related business. Scott (2010) further emphasized that the company may need to spend additional money to retrain staff and recruit professionals. Lim et al. (2010) also mentioned that construction companies practise this strategy only when the demand for construction projects is limited. If the demand is still high, the construction companies do no need diversify business to other non-construction related areas to increase revenue. In addition, some respondents also commented in the questionnaire form that the construction companies should think positively that the market will be fully revived in the future because there is still a considerable amount of demands for projects in Sarawak. However, a high standard deviation of 1.06 indicates that there are differing opinions between the respondents.

Based on the findings, “increasing staff working hours” is ranked the 52th with a mean value of 2.67 and a standard deviation of 0.53. Extensive literature review revealed that this strategy was not commonly adopted by the construction industry. It was only adopted by the Ireland construction industry during the 2007-2012 recession (Tansey et al., 2013). In Malaysia, as set out in the Employment Act 1955, the maximum working hour per week is 45 hours. If the worker’s working hours exceed this limit, the construction company needs to pay overtime wages to his workers. Thus, this strategy does not help to overcome the economic impacts and may exacerbate the company’s financial burden. Besides that, stress related to long working hours can lead to depression and hypertension, thus reducing the workplace effiency (Anandan, 2020).

“Converting permanent staff into temporary placements” is ranked the last (53th) in the present study with a mean value of 2.49 and a low standard deviation of 0.50. It is categorized as an “unimportant” strategy. This finding is matched with the previous studies conducted by Lim et al. (2010) and Scott (2011) who revealed that it is ineffective in reducing employments expenditure. The present study also discovered that only 12.8% of the respondents faced labour redundancy, while 72.1% of them have faced labour shortage during the challenging period. This strategy might increase the risk of worker resignation and further intensity the labour shortage issue.

CONCLUSION

The economic outlook of Malaysia in 2024 is still uncertain due to the presence of some challenges. Therefore, the construction industry should pre-plan strategies to cope with future challenging economic climate. The present study had achieved both research objectives by identifying and prioritizing the survival strategies according to the data collected from the respondents. The present study revealed that “implementing stricter site management to reduce material and time wastage in order to achieve lowest construction cost”, “carefully considering the payment terms and the client ability to make payment”, and “Implementing stricter financial management on company cash flow” are the top three important strategies from Grade 7 construction companies’ perspective. This study may serve as a reference to the construction companies in Sarawak so that they would respond effectively and be able to survive when the economic environment becomes challenging.

FUTURE DIRECTION

Future research can extend the scope of the present study by including Grade 1 to Grade 7 construction companies as well as developers firms, consultants firms and real estate companies who also take part in the construction industry. Besides, similar research can also be extended to other parts of Malaysia to collect more comprehensive data from the construction industry. In addition, other research methods such as qualitative or mixed-methods can be adopted to obtain in-depth information.

ACKNOWLEDGMENT

The work described in this paper was fully supported by University of Technology Sarawak (UTS) research grant (UCTS/RESEARCH/3/2021/05).

REFERENCES

  1. Abubakar, H. O., Danazumi, U. Y., Mairiga, J. A., & Jibrin, M. (2022). Survival strategies of construction firm in Nigeria during recession period: A case study of building construction firm in Nasarawa state. Global Journal of Built Environment, 4(1), 72-79.
  2. Adegbembo, T. F., Ajiferuke, O. O. & Ogbodo, V. (2020). Survival strategies of quantity surveying firms in Lagos State, Nigeria during economic recession. The Lagos Journal of Environmental Studies, 10(2), 84-95.
  3. Adewuyi, T. O. and Otali, M. (2017). Corporate strategies and performance of construction firms in a recessed economy in Niger Delta, Nigeria. Journal of Contemporary in the Built Environment, 1(1), 136-148.
  4. Aghimien, D. O., Aghimien, E. I., Fadiyimu, A. O. & Adegbembo, T. F. (2018). Survival strategies of built environment organisations in a challenging economy. Engineering, Construction and Architectural Management, 25(7), 861-876.
  5. Al-Keim, A. (2017). Strategies to reduce cost overruns and schedule delays in construction projects. [Unpublished doctoral thesis], Walden University.
  6. Al-Tobi, Y. K. and Manchiryal, R. K. (2020). A strategy to overcome the effect of economic recession on construction industry in Oman. Journal of Student Research. https://doi.org/10.47611/jsr.vi.880
  7. Apuke, O. D. (2017). Quantitative research methods a synopsis approach. Arabian Journal of Business and Management Review, 6(10), 40-47.
  8. Bakar, A. H. A., Yusof, M. N., Awang, A. & Adamy, A. (2011). Survival strategies of construction companies in Malaysia during two periods of recession. International Journal of Academic Research, 3(4), 481-486.
  9. Bhagatkar, S. V., Jaiswal, R., Kulkarni, R., Mehta, S. & Lature, A. (2015). Consequences of economic downturn on construction industry and its remedies. International Journal of Civil Engineering and Technology, 6(2), 79-86.
  10. Buys, F. & Rooyen, V. R. (2014). The strategic management of construction companies during recessionary cycles. Acta Structilia, 21(1), 1-21.
  11. Creswell, J. W. & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches. 5th ed. Los Angeles: Sage Publications, Inc.
  12. Department of Statistics Malaysia. (2020). Malaysia Economic Performance Fourth Quarter 2020. Kuala Lumpur: Department of Statistics Malaysia.
  13. Department of Statistics Malaysia. (2021). Malaysia Economic Performance First Quarter 2021. Kuala Lumpur: Department of Statistics Malaysia.
  14. Edmund, B. T., Yang, H. & Eric, A. (2018). A general overview of the impact of global financial crisis on construction industries. ICCREM 2018: Analysis of Real Estate and the Construction Industry, 28-38.
  15. Esa, M. B., Ibrahim, F. S. B. & Kamal, E. B. M. (2020). Covid-19 pandemic lockdown: The consequences towards project success in Malaysian construction industry. Advances in Science, Technology and Engineering Systems Journal, 5(5), 973-983.
  16. Ezeanyeji, C. I., Imoagwu, C. P., & Maureen, I. (2019). Impact of recession on economic growth in Nigeria. International Journal of Economics, Commerce and Management, 7(4), 207-221.
  17. Fellows, R. & Liu, A. (2015). Research methods for construction (4th ed.). Oxford: Blackwell Publishing.
  18. Gamil, Y. & Alhagar, A. (2020). The impact of pandemic crisis on the survival of construction industry: A case of Covid-19. Mediterranean Journal of Social Sciences, 11(4), 122-128.
  19. Hossen, M. M., Kang, S. & Kim, J. (2015). Construction schedule delay risk assessment by using combined AHPRII methodology for an international NPP project. Nuclear Engineering and Technology, 47(3), 362–379.
  20. Jayalath, C. (2023). Survival strategies in the economic recession at firm level: The case of large scale construction companies in Sri Lanka. Journal of Economics, Management and Trade, 29(10), 67-76.
  21. Kam K. J., Lim, T. S., Lee, L. H., Soon, L. T., Leong, B. T., Kamarazaly, M. A. (2022). Survival strategies and challenges faced by subcontractors in Malaysian construction industry. Malaysian Construction Research Journal, 15(1), 22-37.
  22. Lagat, D. K., Njuguna, M., Mutanu, M, Mwende, A., Magak, A., Nyakondo, S. (2023). Strategies towards business continuity for construction industry in Kenya during and after covid-19 pandemic. Current Urban Studies, 2023(11), 367-382.
  23. Liew, C. Y. as cited in Ismail, Z. (2024, Jan 2), Malaysia’s economy in 2024 to stand pat? https://www.sinardaily.my/article/214422/focus/malaysias-economy-in-2024-to-stand-pat
  24. Lim, B. T. H., Oo, B. L. & Ling, F. (2010). The survival strategies of Singapore contractors in prolonged recession. Engineering, Construction and Architectural Management, 17(4), 387-403.
  25. Mohamed, N. H., & Kamaruding, M. (2023). The impact of Covid-19 and construction business survival strategies: A review. Journal of Sustainable Civil Engineering and Technology, 2(1), 1-7.
  26. Norhaidin, N. A. F., & Tan. C. K. (2023). Strategies by the construction companies in Malaysia to survive from the impacts of the Covid-19 pandemic. Journal of Architecture, Planning & Construction Management, 13(1), 17-28.
  27. Ogbu, C.P. (2017). Survival practices of indigenous construction firms in Nigeria. International Journal of Construction Management, 18(1), 78-91.
  28. Olowa, T., Adebiyi, R. T. and Yusuf, G. A. (2018). Strategies adopted by Nigerian Construction Firms in a Recessive Economy [Paper presentation]. Nigerian Institute of Quantity Surveyors: 3rd Research Conference, Bauchi, Nigeria.
  29. Ruddock, L., Kheir, A. & Ruddock, S. (2014). UK construction companies’ strategies in the face of business cycles. International Journal of Strategic Property Management, 18(3), 225-237.
  30. Scott, B. (2011). Survival strategies of services subcontracting firms in an economic downturn (Unpublished degree’s dissertation). Unitec, New Zealand.
  31. Sekaran, U., & Bougie, R. (2016). Research methods for business: A skill building approach (7th ed.). United Kingdom: John Wiley and Sons Ltd.
  32. Tan, A. L. (2021, April 29). Rising steel prices hurting building sector. https://www.edgeprop.my/content/1838109/rising-steel-prices-hurting-building-sector
  33. Tansey, P., Meng, X. & Cleland, D. (2013). A critical review of response strategies adopted by construction companies during an economic recession. In Proceedings of the 29th Annual ARCOM Conference, Association of Researchers in Construction Management, Reading, pp. 679-689.
  34. Toh, K. I. (2020, May 6). Construction firms face another stumbling block. https://www.thestar.com.my/business/business-news/2020/05/06/another-stumbling-block-for-construction-firms
  35. Toh, T. C., Chong, Y. C., Liew, Y. L., Goh, K. C., Zainordin, N., & Lee, C. K. (2023). Survival strategies of Klang Valley Malaysian small and medium building contractors in the post-Covid-19 era. Malaysian Construction Research Journal, 18(1), 189-204.
  36. Ye, K., Shen, L. & Tan, Y. (2010) Response strategies to the competition in the Chinese construction market. Construction Management and Economics, 28(2), 115–24.
  37. Yuan, H. (2013). Critical management measures contributing to construction waste management: evidence from construction projects in China. Project Management Journal. 44 (4), 101–112.
  38. Zamani, S. H., Rahman, R. A., Fauzi, M. A. & Yusof, L. M. (2021). Effect of Covid- 19 on building construction projects: Impact and response mechanisms. IOP Conference Series: Earth and Environmental Science, 682(1), p. 012049
  39. Zuo, J., Zillante, G., Xia, B., Chan, A. & Zhao, Z. (2015). How Australian Construction Contractors Responded to the Economic Downturn. International Journal of Strategic Property Management, 19(3), 245-259.

Article Statistics

Track views and downloads to measure the impact and reach of your article.

2

PDF Downloads

44 views

Metrics

PlumX

Altmetrics

Paper Submission Deadline

GET OUR MONTHLY NEWSLETTER

Subscribe to Our Newsletter

Sign up for our newsletter, to get updates regarding the Call for Paper, Papers & Research.

    Subscribe to Our Newsletter

    Sign up for our newsletter, to get updates regarding the Call for Paper, Papers & Research.